Chapter 18: Managing product delivery Flashcards
What is the purpose of the Managing product delivery process?
The purpose is to control the link between the project manager and the team manager(s), by agreeing the requirements for acceptance, execution and delivery.
What are the objectives of the Managing product delivery process?
The objective of managing product delivery process is to ensure that:
- Work on products allocated to the team is authorised and agreed
- Team managers, team members and suppliers are clear as to what is to be produced and what
is the expected effort, cost or timescales - The planned products are delivered to expectations and within tolerance
- Accurate progress information is provided to the project manager at an agreed frequency to
ensure that expectations are managed.
What are the 3 activities within the Managing product delivery process?
- Accept a work package
- Execute a work package
- Deliver a work package
What do the Team Manager and the Project Manager do in the Accept a work package activity?
They find an agreement as to what is to be delivered.
Including: reporting requirements, constraints, procedures that need to be applied etc.
The Team Manager is responsible for creating a Team plan. Who approves?
The Project Manager and the Senior Supplier.
TRUE or FALSE:
It is recommended (if not even enforced) to develop a Team Plan at the same time as the Stage Plan.
TRUE
This enable the plans to be aligned.
TRUE or FALSE:
When the work package tolerances are to be exceeded, the Team Manager should escalate the issue to the Senior Supplier.
FALSE
The Team Manager should escalate the issue to the Project Manager.
What should the Team Manager do when they are ready to deliver a work package?
- verify the quality register to confirm that the quality activities are complete
- review approval records to verify that all the products to be delivered are approved
- update the team plan to show that the work package is complete
- check the work package and follow the procedure to deliver the completed products
- notify the project manager that the work package is complete
What is an approval record?
A former confirmation that the product is complete.