Chapter 18 Discharge Of Contracts Flashcards
Ordinary method of discharging obligations under a contract
Performance
Condition
Stipulation or prerequisite in a contract, will, or other instrument
When the occurances or non occurrence of an event affects the duty of a party to perform a contract
Classified as:
- conditions precedent
- conditions subsequent
- concurrent conditions
Condition precedent
Event that if unsatisfied would mean that no rights would arise under a contract
Condition must occur before a party to a contract has an obligation to perform under the contract
Energy transfer partners(ETP) v. Enter. Prods. Partners
- ETP and Enterprise had agreements exploring pipeline project
- agreements included a clause that nothing would be deemed to constitute a joint venture UNLESS otherwise authorized by a board of directors (condition precedent)
- Enterprise ended up working with a different company on a successful pipeline
- ETP sued on the basis that they had a common law partnership and this breached fiduciary loyalty
- original ruling for ETP was appealed
- appeal judgement for Enterprise as the condition precedent expressly negated the formation of a partnership
Condition subsequent
Event whose occurances or lack thereof terminates a contract
The happening of the condition subsequent extinguishes the duty thereafter to perform
“Where [conditions subsequent are] ambiguous, are construed against forfeiture.”
Concurrent conditions
The performances of the parties in most bilateral contracts are concurrent conditions that take place simultaneously
(Conditional on each other?)
Normal discharge of contracts
In most cases when the parties perform their promises the contract ceases to exist/ is discharged
May also be discharged by passage of time past specified expiration period
Performance
Doing an act or making of payment
Tender
An offer to perform
Goods have arrived, are available for pickup, and the buyer is notified
Refusal of a tender can be the basis of a lawsuit
Tender of payment= making a payment of the amount owed
Application of payments when multiple debts exist
If debtor specifies which debt is to be paid and the creditor accepts the money they are bound to apply the money as specified
Payments by check
Actually a conditional payment until the money transfers. If transfer fails suit may be brought on either the debt or the check
Mail and timing of payment
Generally held that payment is made on time if mailed on or before final date of payment
Birznieks v. Cooper
- cooper buying land from Birznieks, with payment due Jan 30th
- payment mailed on Jan 30th, received on Feb 1st. Birznieks tried to evict for late payment
- custom to regard mailing check as paying debt means that payment was made on time even though received late
Time of performance
When date or period of time for performance is specified in the contract, performance should be made on that date/ within that period
If no time specified the obligation to perform in a reasonable time is implied (lack of of specification does not impair the contract)
Contracts when time is essential
When “time is of the essence”
Failure to perform by specified time (unambiguously fixed in the contract) can entitle other party to damages
Provision that time is of the essence may be waived
Substantial perfomance
Equitable rule that I’d a good faith attempt to perform does not precisely meet the terms of the agreement, the agreement will still be considered complete if the essential purpose of the contract is accomplished
(Perfect performance not always possible)
Determined by particular circumstances of case
Cost of completion damages
When building contractor has substantially performed but construction is not perfect the contractor is responsible for the cost of repairing or correcting the defects
This offsets the contract price
If cost of completion would be unreasonably disproportionate to the importance of the defect then the measure of the damages is the diminution in the value of the building due to defective performance
Failure to substantially perform
Will not be able to sue to collect payment for additional work AND liable for reasonable cost of bringing work into conformance with contract
Wilfulness of departure from specifications
Does not preclude some recovery but will be a consideration for whether there was substantial performance
Fault of the complaining party
A party cannot complain that performance was defective if the performance followed all terms and specifications of the contract and perhaps those specifications were defective