Chapter 11: Project Control Flashcards
1
Q
purpose of control
A
regulation of results through alteration of activities, allocation of organizational assets
2
Q
three types of control processes
A
cybernetic, go/no-go, post control
3
Q
cybernetic
A
constantly monitored system, negative feedback loop
4
Q
go/no-go
A
testing to see if present condition met, most common, cannot be based on calendar
5
Q
purpose of formal change control system
A
review all changes, identify all task impacts, translate impacts into scope/cost/schedule, evaluate benefits/costs, id alternative changes, accept or reject, communicate, ensure implementation, report