Chapter 10 & 11 Flashcards

Making capital investment decisions; Project analysis and evaluation

1
Q

Relevant cash flows

A
  • The cash flows that should be included in a capital budgeting analysis are those that will only occur (or not occur!) if the project is accepted.
  • Change in the firm’s overall future cash flow that comes as a direct
    consequence of the decision to take the project.
  • These cash flows are called incremental cash flows.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Stand-alone principle

A

The stand-alone principle allows us to analyze each project in isolation from the firm simply by focusing on incremental cash flows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Common types of cash flows

A

Sunk costs
Opportunity costs
Side effects
Changes in net working capital
Financing costs
Taxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sunk costs

A

A cost already paid or have already incurred the liability to pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Opportunity cost

A

The most valuable alternative that is given up if a particular investment is undertaken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Side effects

A

Incremental cash flows for a project include all the resulting changes in the firm’s future cash flows.
Erosion: negative impact on the cash flows of an existing product from the introduction of a new product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Net working capital

A

The project may also entail NWC requirement. NWC typically can be recovered fully (at book value) at the end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Operating cash flow (OCF)

A

OCF = EBIT + depreciation - taxes
OCF = net income + depreciation (when there is no interest expense)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cash Flow from Assets (CFFA)

A

Cash Flow from Assets (CFFA) = OCF - net capital spending (NCS) - changes in NWC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Pro forms financial statement

A

Financial statements projecting future years’ operations.
Unit sales (Q)
Revenues (P)
Variable costs (VC)
Total fixed costs (FC)
Total investment required (NFA)
Investment in NWC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Depreciation

A

Depreciation is a non-cash expense, it is only relevant because it affects taxes.
Depreciation tax shield = D * T
D=depreciation expense
T=marginal tax rate

Straight-line depreciation = initial cost / number of years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

OCF Bottom-up approach

A

OCF = NI + depreciation
Only works only when there is no interest expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

OCF Tax shield approach

A

OCF = (sales-costs)(1-T) + depreciation*T

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

OCF Top-down approach

A

OCF = Sales - Costs - Taxes
Do not subtract non-cash deductions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Equivalent Annual Cost (EAC)

A

The present value of project’s costs calculated on an annual basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Forecasting risk

A

The possibility that errors in projected cash flows will lead to incorrect decisions.

15
Q

Scenario and what-if analyses

A

Scenario analysis: investigation of impacts on NPV by changes in assumptions about a group of variables
▪ Best case – high revenues, low costs
▪ Worst case – low revenues, high costs
▪ Measures of the range of possible outcomes

we examine many variables taking on few different values, in combination.

16
Q

Sensitivity analysis

A

Subset of scenario analysis where we are looking at the effect of specific variables on NPV.
The greater the volatility in NPV in relation to a specific variable, the larger the forecasting risk associated with that variable, and the more attention we want to pay its estimation.

we examine one variable taking on many different values, one variable at a time.

17
Q

Simulation analysis

A

Expanded sensitivity and scenario analysis. Simulation can estimate thousands of possible outcomes based on conditional probability distributions and constrains for each of the variables.
The output is a probability distribution for NPV with an estimate of the
probability of obtaining a positive net present value.

combination of the two: we examine many variables taking on many different values, in combination.

18
Q

Break-even analysis

A

Form of sensitivity analysis. Variable that leads to NPV=0

▪ Total variable costs = quantity × cost per unit
▪ Fixed costs are constant, regardless of output, over some time period.
▪ Total costs = fixed + variable = FC + VC*Q

19
Q

Average vs marginal cost

A

Average cost: TC/number of units ; will decrease as number of units increases

Marginal cost: the cost to produce one more unit, same as variable cost per unit

20
Q

3 types of break-even analysis

A
  • Accounting Break-even
    Where NI = 0
    Q = (FC + D)/(P – VC)
  • Cash Break-even
    Where OCF = 0
    Q = (FC + OCF)/(P – VC); (ignoring taxes)
  • Financial Break-even
    Where NPV = 0
  • Cash BE < Accounting BE < Financial BE
21
Q

Operating leverage

A

The degree or which a firm or project relies on fixed costs.
Degree of operating leverage (DOL) = 1 + (FC/OCF)

22
Q

Capital rationing

A

The situation that exists if a firm has positive NPV projects but cannot find the necessary financing. 2 kinds of capital rationing:
* Soft rationing: the firm itself sets constraints on its various divisions, necessary funds are available at the firm level motivated by maintaining control and keeping track of spending.
* Hard rationing: the firm cannot raise financing for a positive NPV project under any circumstances in its essence, this is due to capital market imperfection