State 3 reasons accidents happen in a construction site.
Lack proper preventive measure
Lack of proper training for operation/workers are not well trained.
Errors in human judgement
State 3 safety practices of falls from.height and struck by falling objects.
- Provide overhead protevtion arnd the building which is under construction
- Provide proper barriers such as guard rail and toe board.
- workers are to put on safety boots.
Name 3 constituents materials of concrete
Aggeregate, Cement & water
Six stages of concrete production
Transporting, Mixing, Batching, Placing, Compacting and Curing.
3 types of test for concrete
Slump test, compacting factor test, compressive strength test
3 types of foundation
Strip foundation, RC pad Foundation, Raft Foundation
3 advantages of using replacement piles.
No risk of ground heave
Can be installed with lesser noise and foundation
Can be installed in very long lengths and very larges bases can be made in favourable grounds.
Explain the difference between end bearing & skin friction piles.
End bearing piles: the shaft of the piles act as columns carryig the loads through the overlaying weak subsoil to a stronger and firmer lower strata in which case the pile gaind most of its support by end bearing.
Skin Friction: the pile passes through the stiff clay and is mainly held up by the frictional resistence between the surface of the pile and the adjoining ground.
3 safety practies for electrocution
Proper earthing, usage of earth leakage circuits and use of personal protective equipment such as boots and gloves.
3 advantages of using displacement piles
Can be driven to a pre determined set
Any construction operations are unaffected by ground water level
Pile’s carrying capacity can be monitored during the piling process.