CHAPTER 1 Flashcards

1
Q

It means estimating of quantities of different items of works.

A

Quantity Surveying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

They make sure that the costs of large construction and infrastructure projects are accurately estimated based on initial requirements and project specifications.

A

Quantity Surveyors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

It is the art and science of predicting the cost of a project before it begins, based on the information available at the time.

A

Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

T YPES OF ESTIMATES

A

Preliminary Estimates
Detailed Estimates
Quantity Estimates
Bid Estimates
Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Gives idea on how much a total project will cost.

Done at the beginning of the project when only limited information isavailable.

A

Preliminary Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contains details of cost, rate, description of all required goods, etc.

Used as a budget estimate.

A

Detailed Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Includes complete quantitative details of material required to complete the project along with its cost

A

Quantity Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Calculated with an expectation to win a project.

Calculated based on standard industry costs or past projects.

A

Bid Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Types of Cost Estimates

A
  1. Historical Estimates
  2. Parametric Estimates
  3. Bottom-up Estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Taken from past similar projects. Usually used for residential projects.

Less accurate and is used only for initial stages.

A

Historical Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Taken using standard per unit rate and then multiplies with the dimensions.

A

Parametric Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The basic work is estimate first and then progressively costs the more complex works.

Should be used only when sufficient information is available.

A

Bottom-up Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

It offers detailed and uniform information to all bidders regarding the project with the aim of soliciting competitive bids.

A

Invitation to Bid (ITB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Variety of operations, procedures, and indirect costs that are not directly linked to construction but are still essential for executing the project successfully.

Includes project management, safety compliance, temporary facilities(TEMFACIL), and waste removal.

A

General Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Terms and conditions or provisions which establish specific and peculiar rights and obligations of the parties involved in the Contract.

Modifies or supplements the general conditions to accommodate specific requirements of a project.

A

Special Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Document that outlines all the terms and conditions of a bid on construction project

A

Bid Form