Chapter 01 - Overview of Building Delivery Process Flashcards

1
Q

Project Delivery Phases

A
Predesign Phase
Design Phase
Preconstruction Phase
Construction Phase
Postconstruction Phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Predesign Phase

A

aka Planning Phase

Project is defined in terms of function, purpose, scope, size and economics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Predesign Tasks

A

Building Program Definition - activities functions and spaces required in the building, along with their approximate size and relationships with each other

Economic Feasibility Assessment - budget and financing

Site Assessment & Selection

Governmental Constraints Assessment

Design Team Selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Design Phase

A
  • Begins with the selection of lead designer (typically the architect)
    Schematic Design Stage
    Design Development Stage
    Construction Documents Stage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

1st Design Phase - Schematic Design

A

Emphasis on Design (creative, conceptual, and innovative aspects of the design)

  • Gives graphic shape to owner’s program: Some elevations, plans, and sketches accompanied by models and computer generated walkthrough/imagery is produced
  • limited consultant involvement
  • Rough estimate of project’s probable cost is produced
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

2nd Design Phase - Design Development

A

Emphasis on Decision Making

  • Consultant involvement to make decisions on exterior envelope, MEPF, structure, etc
  • Vast majority of decisions are made pertaining to products, equipment, and materials
  • More detailed spec and drawings generated
  • GC may be brought on board to provide input about cost and construtability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3rd Design Phase - Construction Doccuments

A

Emphasis on Documentation

  • Prepare all docs required for construction; construction drawings and specifications
  • Construction Drawings show the ‘what’ and ‘where’ of how a building is built to allow for the contractor to execute the ‘how’ and ‘when’
  • Specifications are the written technical description of the design. When assembled with all consultant, this may be referred to as the project manual.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CSI Masterformat

A

Construction Specifications Institute (CSI)

  • Consists of 50 divisions; generally nubered by sequence of work
  • Level 1 digits ( similar to chapters): 00 thru 49 - identify the broadest collection of related products and assemblies
  • Level 2 digits (similar to section): further classify products and assemblies
  • Level 3 digits (similar to subsections) - even further classifies products and assemblies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Preconstruction Phase

A

aka Bid negotiation phase

- Begins after the construction documents are complete and culminates in the selection of the construction teamm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Preconstrcution Phase - Selecting a Contractor

A

Several methods used, the four most common:

  • Competitive bid method
  • Invitation bid method
  • Negotiated contract method
  • Multiple prime contractor method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Preconstrcution Phase - Competitive bid method

A
  • Used on most public projects
  • qualified contractors (via experience and financial standing) are invited to bid (via ads, trade publications, newspapers, etc) on projects based on biding documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Preconstrcution Phase - Invitational bid method

A
  • Similar to competitive bid, but used for private projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Preconstrcution Phase - Negotiated contract method

A
  • Selecting a contractor without a bid process
  • A major advantage of this method is that a contractor can be brought on board during the predesign or design phase and offer preconstruction services
  • Most popular contract method for private work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Preconstrcution Phase - Multiple-prime contracts method

A

aka fast track project delivery
- a variation of the negotiated contract where a project is divides into multiple sequential phases and each phase is awarded to a different prime contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Surety Bonds

A

Surety bonds ensures that should a contractor fail to fulfill contractual obligations, there will be a financially sound party - the surety (aka the guarantor, aka the bonding company) - available to take over those unfulfilled obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Types of bonds: Bid, Performance and Payment

A

Bid Bond aka bid security bond - This bond is required when a bidder submits their bid and insures against frivolous bidders. It insures if selected, a contractor will be able to enter into a contract. If the bidder refuses to enter into the contract, a penalty (usually 5%) is paid to the owner

Performance Bond - Ensures, after the award of contract, that if a contractor cannot complete the contract that a surety will be able to. GCs will in turn require the same for major subcontractors.

Payment Bond aka labor and materials bond - ensures payment by subs and vendors will be paid by GC. Otherwise an owner could be held liable for non payment even if they have paid the GC

17
Q

Pros and Cons of Bonds

A

Pros:
Eliminate financial risk
Cons:
Adds to bid price

18
Q

Construction Phase

A

Commences once GC has been selected and the contract awarded. Construction documents are now contract documents, as they tie the owner and the contractor togeather

19
Q

Construction Phase - Observation of Construction

A
  • Architect provides ‘field observation’ which is periodic and ensures contractor is following contract docs
  • Contractor is responsible for daily supervision and execution
20
Q

Construction Phase - Observation of Construction - ‘Failure to Detect’

A

Although a GC is fully liable for any error in construction, regardless if it was missed by their architect in their observations, the architect can be held liable for not providing timely notification of work not conforming to the contract documents.

21
Q

Construction Phase - Inspection of Work

A

AOR transforms from observer to inspector generally twice in a project: at substantial completion and final completion

22
Q

Summary of Architect’s Typical Functions as Construction Contract Administrator

A

Observe Construction
Inform owner of progress of work
Guards owner against defects and deficiencies
Review and approve submittals
Prepare change orders, if required
Review correspondence between owner and contractor
Prepare certificates of payment
make substantial completion inspection
make final completion inspection
review close out doc submissions
make a judicious interpretation of the contract between owner and contractor

23
Q

Postconstruction Phase

A

aka Project Closeout

  • Commences once contractor requests a substantial completion inspection and passes AOR’s inspection
  • AOR generates a punchlist of incomplete corrective portions of the work
  • Before obtaining a substantial completion, the contractor typically obtains a ‘certificate of occupancy’ form the authority having jurisdiction (usually the city where the permit was filed). The CofO confirms that all appropriate inspections and approvals have taken place and the contractor has demobilized and the owner can occupy the building without obligations to any authority
24
Q

Certificate of Final Completion

A

Contractor completes the close out process and requests a final inspection from the architect. If the inspection passes the AOR issues a ‘certificate of final completion’ and the contractor is entitled to final payment.
The certificate transfers all liability of the site to the owner

25
Q

Alternative Project Delivery Method - Construction Management Method (CM)

A

Owner retains a construction manager as an agent to advise on such aspects as costs, scheduling, site supervision, site safety, construction finance administration, and overall building construction

  • CM is not a contractor and does not have an entrepreneurial role
  • CM is often hired before anybody else
  • There is no GC and the owner awards multiple contracts to various contractors who are them managed by the CM
  • CM method is particularly attractive for knowledgeable owners
26
Q

Alternative Project Delivery Method - Construction Management at Risk Method (CMAR)

A
  • As the CM method has little risk for the CM and the CM does not have direct control of the prime contracts because the contract is directly with he owner, CM evolved into CMAR.
  • Owner pays the CM separately as the CM (with a fee) and as the GC.
  • CMAr works with AOR to develop the project that meets the owner’s budget and needs, this acting as the owner’s agent
27
Q

Alternative Project Delivery Method - Design-Build Method (DB)

A
  • Owner contracts one firm to design and build a project on a cost-plus or lump-sum basis
  • Similar to a historic master-builder meathod
  • Design-build firms are generally contractors with a design team
  • Can lead to shorter projects, and less change orders
  • ‘turn-key’ is a method where the design build team also arranges for land and finances for a project