chap 5 Flashcards
x air is intentionally retained in the mix
entrained
small voids called x are on purpose
entrained air
shotcrete exposed to freezing or thawing should have at least x percent entrained air
4 to 6
dry mix without coarse aggregate is x to x parts cement to sand
one, four
dry mix with moisture in aggregate should be shot x minutes after mixing
45
benefits of predampening dry mix
reduce dust, improve mixing, and reduce static electricity at the nozzle
define wet mix shotcrete
wet-mix shotcrete is the process in which the ingredients, incl water, are mixed before intro to the hose
if aggregate is gap graded, finer sand wil bypass the x and water will separate from the mix, creating x
larger aggregate, bleed water
what happens when bleed water is squeezed from the mix
the aggregate jams, creating a plug in the line
best slump?
50-75mm (2 to 3 in)
wet mix should be used within x min of first x addition
90, water
steel and nonmetallic fibers can be used to improve the x and x of conc
tensile strength, impact resistance