Ch6. Review Test Flashcards
Which of these scheduling techniques is relatively simple and graphically shows the starting and finishing times for individual tasks that make up a job?
A. critical path
B. flow chart
C. bar chart
D. pie chart
C. bar chart
How often should a contractor visit a job site to schedule deliveries, resolve conflicts, and coordinate the work of subcontractors?
A. daily
B. twice a week
C. weekly
D. once a month
A. daily
Which type of surety bond guarantees that the contractor will perform the contract in accordance with its terms and conditions?
A license
B. performance
C. payment
D. bid
B. performance
Which is usually the most difficult item to estimate?
A. labor
B. materials
C. permits
D. equipment rental
A. labor
How much is a 5% retention in dollars if the total job price is $185,000 and company overhead is $37,000?
A. $5,625
B. $7,400
C. $8,325
D. $9,250
D. $9,250