CH.21 ORANGE Flashcards

1
Q

(176) CH.21
PAGE 21-4 .C
Question:
AN INCREASING NUMBER OF ICT PROJECTS ARE DRIVEN BY WHAT METHOD OF SUSTAINABLE BUSINESS PERFORMANCE.

BUSINESS PERFORMANCE IMPROVEMENT=

A

SIX SIGMA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

(176) CH.21
PAGE 21-4 .E
Question:
IN ORDER FOR THE ICT PROFESSIONAL TO IDENTIFY THE BEDT SOLUTIONS FOR THEIR CLIENT NEEDS THE MAY HAVE TO PROVIDE ?
IDENTIFY CLIENT SOLUTIONS-=

A
  1. BUDGET NUMBERS
  2. TIME CONSTRAINTS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

(177) CH.21
PAGE 21-5 .B
Question:
GOOD PM =

A

ABILITY TO COORDINATE WITH DIVERSE GROUPS OF PEOPLE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

(177) CH.21
PAGE 21-5 .D
Question:
A GOOD DESIGNER COULD BE ALSO BE___________?

A

PROJECT MANAGER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

(178) CH.21
PAGE 21-7 .B
Question:
INSTALLATION ISSUES REQUIRE COORDINATION WITH WHOM?
INSTALLATION ISSUES=

A

JOBSITE SUPERVISORS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

(179) CH.21
PAGE 21-8 .B
Question:
A TELECOMMUNICATIONS PROJECT MANAGER PERFORMS PROCUREMENT OF WHAT TWO TYPES?

A

BULK PURCHASES
JUST-IN -TIME PROCUREMENT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

(179) CH.21
PAGE 21-8 .D
Question:
WHEN AN ICT DESIGNER MAY BE REQUIRED TO DO WHAT?
DESIGNER =

A

REVIEW PURCHASE ORDERS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(180) CH.21
PAGE 21-11 .B
Question:
AT A MINIMUM THE SCOPE OF WORK DOCUMENT MUST COVER?
SCOPE OF WORK=

A

1.WHAT TO BE DONE
2.WHEN TO BE DONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

(181) CH.21
PAGE 21-12 .B
Question:
THE FOLLOWING SHOULD BE CONSIDERED FOR INCLUSION IN A COMPREHENSIVE WORKING OUTLINE?
WORKING OUTLINE =

A

1.THE CONTEXT OF RHE PROJECT
2. THE TECHNICAL CONSIDERATIONS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

(182) CH.21
PAGE 21-15 .B
Question:
IT THE ITS DESIGNER IS ASKED FOR O RETROFIT AN EXISTING BUILDING?
SITE SURVEY=

A

REVIEW ANY EXISTING DOCUMENTATION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

(183) CH.21
PAGE 21-18 .E
Question:
DOCUMENT LIFE CYCLE OF PROJECT

A

1.BY CONTRACTOR
2.IN WORK BREAKDOWNS STRUCTURE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

(183) CH.21
PAGE 21-18 .F
Question:
WHAT IS A WBS=

A

WORK BREAKDOWN STRUCTURE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

(184) CH.21
PAGE 21-21 .B
Question:
WHAT TWO SCHEDULING METHODS USE DIAGRAMS?
SCHEDULE METHODS WITH DIAGRAMS?NAME TWO?

A

1.PERT
2. CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

(184) CH.21
PAGE 21-21 .D
Question:
CABLE PLACEMENT IS GOING TO BE COMPLETED IN PROJECT WEEK WHAT ?
AND WHAT PROJECT MONTH?
CABLE PLACEMENT SCHEDULE =

A

1.JUNE
2. WEEK 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

(185) CH.21
PAGE 21-23 .B
Question:
WHAT IS AN ANALOGOUS ESTIMATE?
ANALOGOUS ESTIMATE=

A

TIME/COST FOR A SIMILAR PROJECT IN THE PAST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

(185) CH.21
PAGE 21-23 .D
Question:
IF YOU HAVE A PROJECT IN CHICAGO AND NOW YOU ARE DOING A SIMILAR PROJECT IN NEW YORK WHAT ESTIMATING METHID SHOULD THE DESIGNER USE?
CHICAGO & NEW YORK PROJECT COMPARISON =

A

USE PAST INFORMATION WITH CAUTION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

(186) CH.21
PAGE 21-33 .C
Question:
THE CLOSE OUT OF THE PROJECT WILL BE MANAGED AND APPROVED BY WHO?
CLOSEOUT OF PROJECT MANAGED BY=

A

THE DESIGNER

18
Q

(186) CH.21
PAGE 21-33 .E
Question:
WHAT SHOULD THE CLOSEOUT PLAN INCLUDE?
CLOSEOUT PLAN SHOULD INCLUDE

A
  1. SPARE PARTS
  2. TRAINING RECORDS
19
Q

(187) CH.21
PAGE 21-34 .B
Question:
WHO HIRES THE ARCHITECT?
HIRES ARCHITECT =

20
Q

(187) CH.21
PAGE 21-34 .D
Question:
WHO IS THE ONLY PERSON ON THE DESIGN TEAM THAT IS A LICENSED DESIGNED PROFESSIONAL BY THE STATE OR THE LOCAL AUTHORITY?
LICENSED DESIGN PROFESSIONAL =

A

THE ENGINEER

21
Q

(188) CH.21
PAGE 21-35 .B
Question:
WHAT DOES SD MEAN ?

A

IT MEANS “ SCHEMATIC DESIGN “

22
Q

(188) CH.21
PAGE 21-35 .D
Question:
DESIGN CONFLICTS RESOLVED

A

EARLY IN THE PROCESS

23
Q

(188) CH.21
PAGE 21-35 .F
Question:
AN ICT DESIGNER MAY BE ALSO TASKED WITH?
ICT DESIGNER IS TASKED WITH=

A

EVALUATING STANDARDS AND CODE

24
Q

(189) CH.21
PAGE 21-36 .B
Question:
STEPS TAKEN DURING BIDDING PHASE CAN INCLUDE

A

RESPONSE EVALUATION

25
(189) CH.21 PAGE 21-36 .E Question: DURING THE BID PROCESS, WHAT IS THE DESIGN TEAM DOING? DESIGN TEAM ACTIONS DURING BID PROCESS=
EVALUATING, NEGOTIATING, CONSIDERING ALTERNATES
26
(190) CH.21 PAGE 21-36 .B Question: RFQ=
PROVIDES MORE DETAIL WITH MATERIAL, EQUIPMENT, COMPONENTS
27
(191) CH.21 PAGE 21-37 .B Question: ONCE BIDS ARE RECEIVED FROM THE CONTRACTORS, THE OWNER AND DESIGN PROFESSIONAL WILL REVIEW DESIGN BID BUILDS TO DO WHAT ? REVIEW DESIGN BID BUILD =
AWARD CONTRACT
28
(192) CH.21 PAGE 21-38 .B Question: WHAT TWO TYPES OF BIDS GET AWARDED? TWO BID TYPES=
1.LOW BID 2.NEGOTIATED BID
29
(192) CH.21 PAGE 21-38 .D Question: THE ICT DISTRIBUTION DESIGNER RESPONSIBILITY IS COMPLIANCE WITH ? ICT DISTRIBUTION DESIGNERS RESPONSIBILITY =
CONTRACT DOCUMENTS
30
(193) CH.21 PAGE 21-39 .B Question: WHAT IS THE REASON OF THE DESIGN TEAM COORDINATING WITH THE STEAK HOLDERS? DESIGN TEAM MAY COORDINATE WITH STEAK HOLDERS=
TO RESOLVE CONFLICTS
31
(194) CH.21 PAGE 21-40 .B Question: WHAT TYPE OF CONTRACT IS A STIPULATED SUM ? STIPULATED SUM=
FIXED PRICE CONTRACT
32
(194) CH.21 PAGE 21-40 .D Question: WHAT IS A COST PLUS FEE CONTRACT? COST PLUS=
REIMBURSED PLUS A FEE
33
(194) CH.21 PAGE 21-40 .F Question: WHAT IS USED TO FACILITATE MINOR FIELD CHANGES TO THE REQUIREMENTS? FIELD ORDER=
MINOR CHANGES
34
(194) CH.21 PAGE 21-40 .H Question: WHAT IS A CHANGE ORDERS ? CHANGE ORDERS =
FORMAL DOCUMENTS DEFINING CHANGES
35
(194) CH.21 PAGE 21-40 .J Question: SUBMITTAL=
DESIGN TEAM FOR APPROVAL
36
37
(194) CH.21 PAGE 21-40 .M Question: WHAT DO YOU DO IF A MATERIAL FOR A PROJECT IS NOT AVAILABLE? MATERIALS UNAVAILABLE =
SUBMIT ALTERNATIVE THAT MEETS ORIGINAL SPEC
38
(194) CH.21 PAGE 21-40 .O Question: IN THE EVENT THAT SUBMITTALIS REJECTED , THE DESIGNER MAY NEED TO ? TWO ANSWERS SUBMITTAL REJECTED=
1. REVIEW CONTRACT 2.REQUEST VARIANCE
39
(194) CH.21 PAGE 21-40 .Q Question: SOME OF THE ITEMS THAT THE CONTRACTOR WILL NEED TO SUBMIT ARE? CONTRACTOR MUST SUBMIT=
1. SHOP DRAWINGS 2. TEST REPORTS
40
(195) CH.21 PAGE 21-42 .B Question: WHO IS RESPONSIBLE FOR FINALIZING MOVE IN AND FIRST USE ACTIVITIES? MOVE-IN & FIRST USE=
ARCHITECT AND CONTRUCTION MANAGER
41
42