High-Pressure Engines: Two-stage 1000 gpm or 2000 gpm engines retro-fitted with
a ____________ and have been issued specialized highpressure
equipment to pump at discharge pressures over ____ psi and up to ____ psi.
a special high-pressure discharge elbow,
250psi , 600psi
Sec 1.1
3rd Stage Engines: An engine with a 3rd Stage. This 3rd Stage can supply a maximum
of ____ gpm up to ____ psi.
500 , 700
Sec 1.1
357
High-pressure and 3rd-stage engines have the following specialized equipment ?
3” high-pressure supply hose, 50’ per length.
High-pressure fittings. (painted white, heavier)
High-pressure outlets.
o One HP outlet on HP Engines.
o Two HP outlets on 3rd Stage Engines.
Tether straps with gated hooks.
Sec 1.2
Can conventional engines operate in excess of 250 psi ?
YES!
Unless emergency conditions exist AND they are ordered to do so by the IC,
conventional engines should not operate in pressures exceeding 250 psi
Sec 1.4
Fire on the 75th floor , what is the operating pressure needed ?
500psi doofus
Check Table 2 in Sec 2.1
At what pressure is to be considered High Pressure Operations ?
Excess of 250 psi!
Sec 2.2
Prior to starting high-pressure pumping what must first be established ?
A safety zone must be established on each side
of the engine and high-pressure supply hose. Warning tape, rope or stanchions are to be
used to designate this zone
Sec 3.1
Maintain safety zones of at least _____ around a working engine in all directions
including the high-pressure supply hose.
50 feet
Sec 3.1
When using high pressure hose for high pressure pumping no more than 3 lengths shall be stretched from pumper to siamese. Agree or Disagree
Disagree fool!!
Whenever possible, an engine supplying high-pressure should be positioned within 1 hose
length of the fire department connection being supplied.
No more than 2 connected lengths
of high-pressure supply hose should be stretched to the fire department connection
Sec 3.1
In an extreme emergency High pressure or 3rd stage pumpers can use standard 3 1/2” as a supply line. True or False
FALSE!! MUST USE
Specially trained and equipped ‘High-Pressure’ or ‘3rd Stage’ engines MUST use their
high-pressure supply hose, fittings (painted white and noticeably heavier than
conventional fittings) and tether strap
Sec 3.1
When operating in high pressure should the gates and outlets be closed ?
YES!!
All unused gates and outlets on the apparatus MUST be closed and capped. All caps must
be secured tightly.
Sec 3.1
Each engine operating at high-pressure must be controlled by the ECC and assisted by Who ? And shall do what ?
ECC from a non-pumping engine. One ECC shall operate the pump and one ECC shall
monitor radio communications. Other ECCs of non-pumping engines shall assist in
keeping persons out of the safety zone.
Sec 3.1
High pressure hose MUST be secured using the tether straps . At what points are the secured ? 1-3 What if tether straps unavailable ?
The tether strap shall be secured to
both the engine and the building fire department connection.
When more than one length of hose is required, each length must be tethered and secured
to each other by the tether gated hook
No Tether use utility rope! secure apparatus and siamese
Sec 3.1
During high pressure ops. stairwells served by standpipes are a good place to use as a rest area so as members can monitor system ?
NO!!
Stairwells served by standpipes must not be used as staging or rest areas during high
pressure pumping operations. Use a minimum amount of operating personnel in these
stairways.
Sec 3.1
Preset pressures on apparatus equipped with pressure governors, should be used when
charging a standpipe system. Agree or Disagree
Disagree!!
Preset pressures on apparatus equipped with pressure governors, should not be used when
charging a standpipe system. Once the supply line is charged, pressures are to be
increased slowly to avoid damage to the building piping.
Sec 3.1