Ch 7 - Project Cost Management" Flashcards

1
Q

The aggregation of estimated costs of individual activities or work packages to establish a cost baseline is known as what?

A

Cost Aggregation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What is the process of estimating the costs of resources required to complete project work?

A

Cost Estimation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the process of developing an approximation of the monetary resources needed to complete project activities?

A

Estimate Costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a technique that uses the actual cost of previous similar projects as the basis for estimating the cost of the current project?

A

Analogous Estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a detailed approach that estimates the cost by summing the costs of individual activities?

A

Bottom-Up Estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What technique uses a statistical relationship between historical data and other variables to estimate project costs?

A

Parametric Estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The cost baseline is typically established during which process?

A

Determine Budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the approved version of the time-phased project budget, excluding management reserves, used to measure, monitor, and control overall cost performance?

A

Cost Baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline?

A

Determine Budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which reserve is set aside to address the identified risks that remain after the risk response planning process?

A

Contingency Reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which method involves calculating the value of the work performed and comparing it to the actual cost incurred to determine project performance?

A

Earned Value Management (EVM).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the process of monitoring the status of the project to update project costs and manage changes to the cost baseline?

A

Control Costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What reserve is set aside for unidentified risks and typically requires management approval for use?

A

Management Reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the formula to calculate Cost Performance Index (CPI)?

A

CPI = EV / AC (Earned Value / Actual Cost).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the formula to calculate the Schedule Performance Index (SPI)?

A

SPI = EV / PV (Earned Value / Planned Value)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What term refers to the difference between the budget at completion (BAC) and the actual cost?

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the term for the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete (ETC)?

A

Estimate at Completion (EAC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the term for the amount of work scheduled to be completed by a certain date, versus the amount of work actually completed by that date?

A

Schedule Variance (SV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the term for the expected cost to finish all the remaining project work?

A

Estimate to Complete (ETC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the formula for calculating Estimate at Completion (EAC) if the project is expected to continue performing at the current Cost Performance Index (CPI)?

A

EAC = BAC / CPI.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the formula for calculating Estimate at Completion (EAC) when the project is expected to perform at the original budget rate?

A

EAC = AC + (BAC - EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which cost estimating method is the most accurate but time-consuming?

A

Bottom-Up Estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What term describes the predicted difference between the current cost baseline and the expected final project cost?

A

Variance at Completion (VAC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the formula for calculating To-Complete Performance Index (TCPI) based on the budget at completion?

A

TCPI = (BAC - EV) / (BAC - AC)

23
What is the technique called when the total project cost is divided by the total number of units to obtain a per-unit cost?
Unit Cost Estimating.
24
What is the process of determining a budget that allows the project to be completed within the approved funding?
Determine Budget.
25
What term refers to unauthorized deviations from the budget, often caused by poor scope control?
Cost Overrun.
26
What is a periodic reassessment of the work's budget against the baseline called?
Cost Review.
27
What is the time-phased project budget used to measure and control cost performance?
Cost Baseline.
28
What is the systematic approach to managing changes to the cost baseline?
Cost Control. A: Cost Estimation.
29
The aggregation of estimated costs of individual activities or work packages to establish a cost baseline is known as what?
Cost Aggregation.
30
What is the process of developing an approximation of the monetary resources needed to complete project activities?
Estimate Costs.
31
What is a technique that uses the actual cost of previous similar projects as the basis for estimating the cost of the current project?
Analogous Estimating.
32
What is a detailed approach that estimates the cost by summing the costs of individual activities?
Bottom-Up Estimating.
33
What technique uses a statistical relationship between historical data and other variables to estimate project costs?
Parametric Estimating.
34
The cost baseline is typically established during which process?
Determine Budget.
35
What is the approved version of the time-phased project budget, excluding management reserves, used to measure, monitor, and control overall cost performance?
Cost Baseline.
36
What is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline?
Determine Budget.
37
Which reserve is set aside to address the identified risks that remain after the risk response planning process?
Contingency Reserve.
38
What reserve is set aside for unidentified risks and typically requires management approval for use?
Management Reserve
39
What is the process of monitoring the status of the project to update project costs and manage changes to the cost baseline?
Control Costs.
40
Which method involves calculating the value of the work performed and comparing it to the actual cost incurred to determine project performance?
Earned Value Management (EVM).
41
What is the formula to calculate Cost Performance Index (CPI)?
CPI = EV / AC (Earned Value / Actual Cost)
42
What is the formula to calculate the Schedule Performance Index (SPI)?
SPI = EV / PV (Earned Value / Planned Value)
43
What is the term for the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete (ETC)?
Estimate at Completion (EAC).
44
What is the term for the amount of work scheduled to be completed by a certain date, versus the amount of work actually completed by that date?
Schedule Variance (SV)
45
What term refers to the difference between the budget at completion (BAC) and the actual cost?
Cost Variance (CV)
46
What is the term for the expected cost to finish all the remaining project work?
Estimate to Complete (ETC).
47
What is the formula for calculating Estimate at Completion (EAC) if the project is expected to continue performing at the current Cost Performance Index (CPI)?
EAC = BAC / CPI.
48
What is the formula for calculating Estimate at Completion (EAC) when the project is expected to perform at the original budget rate?
EAC = AC + (BAC - EV).
49
What is the formula for calculating To-Complete Performance Index (TCPI) based on the budget at completion?
TCPI = (BAC - EV) / (BAC - AC)
50
What term describes the predicted difference between the current cost baseline and the expected final project cost?
Variance at Completion (VAC).
51
Which cost estimating method is the most accurate but time-consuming?
Bottom-Up Estimating.
52
What is the technique called when the total project cost is divided by the total number of units to obtain a per-unit cost?
Unit Cost Estimating.
53
What is the process of determining a budget that allows the project to be completed within the approved funding?
Determine Budget.
54
What term refers to unauthorized deviations from the budget, often caused by poor scope control?
Cost Overrun.
55
What is a periodic reassessment of the work's budget against the baseline called?
Cost Review.
56
What is the time-phased project budget used to measure and control cost performance?
Cost Baseline.
57
What is the systematic approach to managing changes to the cost baseline?
Cost Control.