CH. 5 Emergency Management/Storm Response Flashcards

0
Q

24 hours a day, 7 days a week

A

24-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

A method to determine the severity and likelihood of risk

A

5X5 matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A process whereby a electricity is fed back into downed lines, usually from a home generator that can re-energize the lines; the voltage can be raised if it passes through a transformer.

A

Back feed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The person at the utility or line clearance company who is in control of sending the line clearance crews to work locations

A

Dispatcher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Properly providing a path for the flow of electricity to prevent accidental energizing of a power line

A

Grounded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Line clearance crews that are on standby 24 hours a day, seven days a week and can be called to an emergency at relatively short notice

A

On call

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A person designated as the leader or controller of an emergency situation or operation

A

Person in charge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Personal safety gear such as hard hat, safety glasses, and hearing protection

A

Personal protective equipment PPE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Distribution lines that carry voltage ranging from 2400 to 34,500 volts

A

Primary lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The process of assessing the risks posed by a job task such that the identified risks can be reduced or eliminated, making the job safer for personnel; process of determining the level of risk posed by a tree or group of trees on a property

A

Risk assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Circuits that carry lower voltages from distribution transformers to the point of use

A

Secondary lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Refers to issues, situations, risks, dangers, and other factors that are unique to a particular worksite or emergency situation

A

Site specific

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Refers to the time when crews are released from a call or 24-7 status to return to normal working hours

A

Stand down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A device used to facilitate communication between two parties such as crews and crew leaders, crew leader and dispatcher, or dispatcher and utility person in charge

A

Two way radio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Safety standards care operations, approved by the American National Standards Institute. These safety standards are for pruning, trimming, repairing, maintaining, and removing trees and cutting brush

A

ANSI Z133.1-2000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Major storms or _____ weather events are the usual cause of power outages over large areas.

A

Catastrophic

16
Q

Crew mobilization for a storm event is much more rapid from a _______status.

A

Standby

17
Q

The _______standards are voluntary safety standards for pruning, trimming, repairing, maintaining and removing trees, and cutting brush.

A

ANSI Z133

18
Q

On a storm site, cutting should not begin until all risks have been assessed in the_______approach decided in adopted.

A

Safest

19
Q

As clearance work progresses,________between crews and dispatcher is critically important to determine locations of downed or damaged lines.

A

Communication

20
Q

One of the highest personal risks and storm work is________.

A

Fatigue

21
Q

Always consider that all lines are_______.

A

Energized

22
Q

The sound of a running home generator should alert crews to the possibility of________.

A

Back feed

23
Q

Crew members should always refer customer questions about the status of power restoration to the_________.

A

Utility

24
Q

Customer relations are important during a storm response but are necessarily a low priority than_______and power restoration.

A

Safety

25
Q

An electrical backfeed may be caused by:

A

And operating home generator

26
Q

When responding to a storm emergency, the highest priority for crews should be to:
A. Remove all trees with past trim refusals
B. Work on circuits with the most tree damage
C. Work on circuits feeding hospitals

A

Work on circuits feeding hospitals

27
Q

When arriving at a storm site, the highest priority for the crew foreman is to immediately identify and locate:
A.down the electrical lines.
B. Downed or damage poles and other equipment.
C. Trees and or branches hanging in the lines.
D. An escape route

A

Downed electrical lines

28
Q

A basic guideline to follow in storm emergency work is two:
A. consider CATV and telephone lines to be safe
B. keep the customer satisfied
C. consider all wires energized
D. cut first and ask questions later

A

Consider all wires energized

29
Q

Which of the following conditions is most likely to fail and causing electrical outage in a moderate storm?
A. An open trunk cavity
B. Code dominant leaders with included bark
C. Overhanging, live branches
D. A D current tree form

A

Overhanging, live branches