Ch 3 - Managing the Information Systems Project Flashcards

1
Q

What is Project Managment?

A

Controlled process of initiating, planning, executing, and closing down a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Phases of Project Management

A
  • Initiating
  • Planning
  • Executing
  • Closing Down
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Management Initiation Phase

A

Where activities are performed to assess the size, scope, & complexity of the project & to establish procedures to support later project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Project Workbook?

A

Online repository for all project- related docs used for audits, orienting new members, communications, identifications, & reviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Project Charter?

A

Doc prepared for the customer during project initiation that describes what the project will deliver & outline at a high level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Management Planning the Project phase

A

2nd phase. Focuses on defining clear, discrete activities & the work needed to complete each activity within a single project. Includes tool like Gantt chart & network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project Managment Executing the Project phase

A

3rd phase. Where plans created in prior phases are put into action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project Management Closing Down the Proejct phase

A

Final phase, focusing on bringing a project to an end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Formula for Estimated Task Duration

A

Estimated Time = ((optomistic + 4(realistic) + pessimistic)) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Critical Path Scheduling?

A

Indicates shortest time in which a project can be completed (meaning no uneccesary delay)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Slack Time?

A

Amount of time that an activity can be delayed without delaying the project; anything no on critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you calculate slack time?

A

Calculate the earliest possible completion time for each activity by summing the activity times in the longest path to activity.
Calculate the latest possible completion time for each activity by subtracting the activity times in path following activity from total expected time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly