Duty holders
A
Client Designer Principal designer Principal contractor Contractors Workers
2
Q
Client duties
A
- appoints PD,PC
- Notifiable, notice to executive as soon as practicable before construction phase - F10
3
Q
Designer duties
A
Eliminating reducing and control foreseeable risk through design.
4
Q
Principal designer duties
A
Designer control over the
- pre construction phase (PCP)
- appointed in writing by client
- planning managing monitoring and coordinating PCP
- work continues in (CP)construction phase when design work is carried out, gathering and preparing info for health and safety file.
5
Q
Principal contractors duties
A
- coordinates the work of CP involving more than one contractor
- appointed by client
- skills knowledge experience
- liaise with PD with regards to
- planning monitoring and coordination
6
Q
Health and safety file duties
A
- PD PREPARES FILE with liaison with client on structure and content
- PD regularly reviewed and updated
- hands to PC to complete
7
Q
Notifiable specs
A
- last longer than 30 days and
- have more than 20 workers working simultaneously.
- exceeds 500 person days