What were the options that were presented to the client?
A
- Split the enabling works packages and procure these separately
- Use a framework
- Engage with local supply chain (contractors) in line with procurement guidelines
- Eric Wright
- William Pye
2
Q
What was the scope of works for the Enabling Works package?
A
- SI, surveys to check utilities on site
- Water Works, new drainage and sewage
- Utility connections, gas, electric
- Private Internet connection
3
Q
Advantages of splitting the enabling and main construction works?
A
- Lower initial investment - manage cash flow. Spread of project costs
- Can still occupy the site
- Time to negotiate the main contract
4
Q
Dis-Advantages of splitting the enabling and main construction works?
A
- More time and resource to procure 2 contractors - more cost
- Longer programme period - can’t overlap diff activities from enabling and construction
- Limit any changes
- Handover of site