Case Study Flashcards
How does the letting of the Fit-Out Contract fit into the Shell and Core Contract? What’s the mechanisms of the contract
The Fitout was included as a defined provisional sum under the S&C Contract. Instructed into the main contract through a deed of variation.
What was the advanced payment for?
It was the mechanism used to reduce inflationary costs received within the tender returns. In relation to my package it was used for the purchasing of stone.
The advanced payment was £4million, and this saved (£300,000)
Why was a deed of variation needed?
In terms of monetary value and scope, this instruction of the fit out works was far too large to be instructed under a simple JCT D&B variation. This was also the mechanism under the contract, so we had to use it.
What does a DOV do?
It amends the existing contract terms due to the large scale nature of the change. Typically this will include;
- date for completion
- any update of LD’s
-the change of the scope of work
adjustment of contract sum
When you were first appointed, what was the personal advice that you gave the Client? (Before the returns)
Carried out a very high-level review to advise how much I believed the returns would be over the pre-tender estimate and why.
When you got the tenders back, you had this one at 43 million and one at 42. What was the difference between this?
- Not solely because the incumbents had priced with inflationary costs.
- Errors were identified, for example there was a doubling up of prelims which removed £250k
- The £42m had missed some areas of scope that the £43m had included, for example FF&E.
Was this completed stone, or what was the status of it? What measures/process did you take to ensure the money was protected.
We had the vesting process which is fully documented, so there are monthly visits to the factory, the visits are recording finished stone and recording the selection of blocks from the quarry, slices after it, book matching and dry laying before it goes into final manufacture. There is an off-site inspection regime with the clients, contractor, stone manufacturer.
Stone is specified by its name, we specified stones from certain/known quarries which set the qualitative level, we then had the right to select blocks but not an infinite amount.
What legislation affects the number of cubicles you mention in your case study?
Building Regulations - Part T was introduced in 2023 but nto clear which one would be before that.
How did you go through identifying what went wrong?
- Reported on the fact that the PTE was done perhaps a little too early in May 2022.
- Used Gleeds extensive market analysis.
-Used my previous project experience of working on bespoke luxury hotels.
What was Gleeds, PTE and market predicting for inflation?
*PTE by incumbents was 8%
*Gleeds were forecasting in excess of 10% but it was fluid market depending on the sector. I had been seeing variances between 10-15% for some packages which enabled me to raise concerns.
*BCIS was 8%
Were you able to identify the inflation costs to confirm if this was worse than the prediction?
I did see inflation costs in the tender returns and they were higher than the G&T one, but we didn’t ask for them for what their ‘inflation costs are’ we said what is your price for fixing, i.e buying the risk. This was a singular line item. Give us a price excluding inflationary costs and below include the cost for fixing, which is what led us into the discussion of advanced payments (example buying sanitary ware, light fittings, custom made brass taps).
It wasn’t the labour that was a concern for inflationary costs, it was the cost of the material that was a concern for the contractor.No, built into the cost.
I assume the £40m was procured over various packages? What was your role in ensuring value for money?
No, not separate packages. Through the D&B we went to a fit-out contract who then went and got the prices from all of the trades (plumbers, dryliners etc) and then the main contractor put his percentage on top for managing it all. I was fully cognisant that there was a degree of doubling up, but given programme requirements it was better to de-risk the projects profile. The certainty of delivery and single point responsibility justified it.
How do you calculate tender inflation?
Using BCIS TPI
How do you calculate to mid-point construction inflation?
Using TPI
How was inflation bought within the packages?
We asked for a lump sum fixed price for the full duration.