Case Study Flashcards

1
Q

What is the difference between outline planning and full planning

A

An option agreement is a two stage process to to able to start construction, full planning permission is a single stage process.

Outline planning seeks permission from the local planning authority for the principle of a design including number of dwellings ,site layout and access. The applicant then has three years to seek approval of reserved matters which include all other matters such as drainage, design, scale, materials, highways public open space.

Full planning permission seeks approval of all matters within one application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What price could have been achieved if you sold the site with the benefit of outline planning permission/self promotion?

A

Value would have to reflect the time, costs and risk put into achieving outline planning permission.

Having compared similar sites and spoken with a local agent I believe a market value of £600,000 could be achieved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you come to a value of £15,000/acre for the land without the benefit of planning permission.

A

Used the comparable method, used local transaction wihtin the area and spoke with local agents. This price reflects the supply and demand in west somerset, scarcity value and hope value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what are the risks associated with disposal of land of this nature?

A

There is risk to both landowner and developer.

No guarantee of sale for the landowner as it is subject to planning permission being gained and the developer still has an option not to purchase although this is unlikely.

Land owner has little control over the development and what planning permission is submitted, as my client lives locally to the development the risk of a bad reputation was important.

Land is not put on the open market meaning the best purchase price may not be achieved, it also does not allow for a completive bidding scenario.

Option agreements are costly for developers as they are responsible for all costs and there is no grantee that these costs will be recovered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What comparable did you make between the offer received and others you had seen

A

Director had agreed a similar site in North Devon used this and made adjustments for different location otherwise nature of the site was similar.

Size of site, access, reference to local plan compatibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What did you advise were the shortfalls of the offer?

A

The main and most important shortfall of the agreement was the low purchase price, looking at comparables it was not a competitive open market offer. This is due to the fact that the offer was on the basis of 14 dwellings including a number of affordable dwellings.

Believed a better offer could be achieved with a private developer who may look to avoid local housing allocation.

Larger site may have been harder to achieve planning and could have taken longer.

Reputation was important, the site did not appear to be sympathetic or in keeping with other developments. Wanted it to be received well by the public

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Talk me through the positives of self promotion and promotion agreements
A

Self promotion allows a landowner to remain in full control of the project, they are responsible for achieving planning permission and marketing the site. They remain in control of what is achieved. A landowner can set their own timescales which work to meet their aims.

Promotion agreements allow the land to go on the open market once planning has been achieved, this allows for the site to reach its true market value and potentially create a competitive buying scenario. The landowner is not bound to sell the land to the promoter once planning has been achieved, which gives them flexibitly. Lastly, both the landowner and promoter have the same interests and aims, meaning the promoter should work hard to achieve a good result for both parties. Promoter is reimbursed for the costs of achieving planning permission on the site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. What appetite to risk would both options require?
A

Self promotion requires the landowner to use their own time and finacnes to implement planning for the site, if planning permission is not gained they risk wasting their time and monies. If the land owner is a layman and does not have development knowledge they require the expertise of professionals which requires a level of trust and more fiancnes.

The terms of a promotion agreement are often longer than an option agreement as it covers planning period and marketing period once planning has been gained. The promoter will deduct their costs of the sale price achieved, not maximising capital from the asset. If marketed during a weak market they may not achieve best value, may cause parties to agree to delay marketing which in turn delays the promotion period which would not meet the clietns objectives.

Both carry a degree of risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Why did the positives outweigh those of the other two options?
A

I think its dependent on each individual land owner, its important to understand their position and objectives to be able to make these decisions.

My client was not in a financial position to implement the planning process herself, in addition ran the farming business with little help and was experiencing issues with the weather and had just experienced a poor harvest. Was not in the right frame of mind to take on such a project.

Client needed to raise capital quickly, understood that an option agreement can achieve a client payment quicker than a promotion as do not have to wait for marketing and conveyancing process.

Option agreement allowed client to choose the developer that would be designing the site and implementing planning permission. Reputation was an important consideration.

Ultimately we were aware that there were few private developers in west somserset, once we had started investigating development potential of the land we were both aware of Tregenna and liked developments we had seen and were aware of their good reputation locally.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Aside from value and time, what other advice did you give your client about disposing of land in this way?
A

Advised the client that a degree of risk management should be considered with option agreements, that drafting heads of terms and negotiations to get the correct terms were important.

Advised on additional payments such as legal and professional fees, that it was normal practice for developer to cover these and considering my clients financial position this was of even more importance.

Consider the impact this would have on the retained adjoining land, it may increase the value of the land and potential of obtaining planning permission.

Also advised that it was important to understand clients tax position if the option agreement was successful.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Did you advise on any sale values for the other options?
A

Advised that if a client wanted to sell land within 6 months we would sell without benefit of planning permission for approx. £90,000. This included an element of hope value.

If we went down self promotion route and obtaind outline planning permission on the site, to then market the site with the benefit of outline planning permsisiosn I would advise a guide price of circa £600,000.

Once the client had an understanding of the promotion agreement process they decided it was not suitable for them so did not get that far with research and potential values.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Did you provide any advice to CGT and potential reliefs?
A

Sought advice from my clients accountant as I was aware that giving detailed taxation advice was outside of the scope of my competence and experience.

Having understood the client tax position, selling the land would provoke a CGT which we believe would be at 20% as client is a higher tax payer. There were two reliefs that may be suitable, business asset disposal reflier and roll over relief. As the client had no desire two cease trading immediately roll over relied seemed the most likely option.

Adivsed that the land in its current state, being farmed under farming business, would have 1005 IHT relied under APR but once turned into cash payment would be taxed at 40% on death. Had little implications to my client as they have no immediate family.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. What is the rationale for advising client to engage with a developer with an existing relationship with ENP?
A

Carhampton village boundary adjoins the Exmoor National Park boundary. Having worked in west somerset and being aware of the planning process I was aware that ENP would have an informal opinion at the consultation period on matter such as impact on landscape and heritage.

If a developer has already overcome this issues they will be able to reflect this within the design and it may mean less issues with consultation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. What was talked about at the site meeting?
A

I ensured that the developer had an understanding of the clients position and objectives. That timescales were important.

Developer informed me of their background, some success stories and basic principles of what could be achieved at the site.

Developer asked if my client had any current or historic disuptes with any adjoining land owners and if there were any issues, such as flooding history, that they should be aware of.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. How would a development of 9 houses at this site for within the crietria for limited development?
A

Carhampton is designated as a primary village where limited development is permitted in certain circumstances
Limited development is defined as individual schemes of up to 10 dwellings that deliver about a 10% increase in the settlements dwelling numbers.
Therefor in principle 9 dwelling houses would be allowed but may meet an affordable housing provision. Understand that 6 or more dwellings would require affordable housing or a financial contribution to financial housing off site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. How many houses would the settlement have to increase by, before meeting the 10% growth gap?
A

At the time that the local plan was produced, I understand the dwelling numbers in carhampton were approx. 317.

Therefor 31/32 dwellings would be required.

17
Q
  1. How many dwellings would the clients development take the number of dwellings to?
A

Believe approx. 329 dwellings

18
Q
  1. Any risks identified by the developer as to the ability to bring the site forwards for development?
A

If the site was to include more than 5 units the site would require an affordable housing provision or a financial contribution offsite making the site unviable

Proximity to Grade II cottage and scheduled ancient monument may require heritage materials to be used, an additional cost to developer

Landscaping impact on ENP during consultation period

Flood risk zone one- needed exploring but not believed to be a big issue

Provide public open space and BNG on site

19
Q
  1. How did developer reasurrse you and your client that they had a good chance of overcoming complications
A

Developer had already gained planning permission for a similar site within the village that had been well received by the village. This gave us confidence in their approach to the system and ultimately their decision making

Would keep the development below the affordable housing provision

Use heritage materials and a mix of single and double storey dwellings to minimise impact

20
Q
  1. How did you rationalise the acceptance of £45K for each unit delivered in next 10 years?
A

Important to secure as would provide the client with a potential retirement fund which would coincide with timings.

Developer originally proposed £40K so it was an increase for client.

Used comparable evidence

If developer could deliver phase one then phase two seemed likely

21
Q
  1. What updates do you have on the project?
A

Due to exchange contracts today, slight delay due to ongoing negotiatons on clients right to approve planning permission and agreeing a suitable long stop date.

The developer has made an expression of interest in the adjoining land, shows that we have successfully achieved a good lating relationship with them. Client has advised that it is of interest of them but they wish to complete this project first and will then take some time to focus on the changing farming business. A period of consolation for them.

Developer has assured me that they are on track to submitte outline planning in early may and does not yet believe there should be any major issues.

22
Q
  1. Can you give me an example of when you acted with integrity with this project?
A

I became aware of the unregistered access a little later on in the process than when I should have. I knew that I should have picked up on this when carry out background research prior to the initial meetings

As soon as I became aware of the issue I was honest and informed my client straight away, I provided my client with a strategy and informed the developer.

The issue was resolved quickly because I acted with integrity and informed client straight away.

23
Q
  1. What is a conflict?
A

Anything that could impede a survbeyors ability to act impartially of in the best interest of their client
Party conflict
Own conflict
Confidential conflict

Conflict of interest 1st edition 2017

Members must identify and manage conflict
Information barriers
Approved informed consent

24
Q

What is informed consent

A

Party who may be affected by a conflict gives willing consent for RICS surveyor to act and that they are aware of the conflict, have been given the facts and are aware that it could impede surveyors ability to act impartially and in best interest

25
Q
  1. How would you set up your own practice
A

Inform RICSof nature of business, staff etc
Appoint responsible principle
Arrange pii
COI/ AML/ CHP policy
Arrange cover in result of death of absence
Sale filing

26
Q
  1. What is the acid test?
A

Allows companies to measure ability to pay off short term liabilities with cash

Principle based approach. GAAP is rule based

27
Q

Pro statement for bribery

A
  1. Countering corruption and bribery, money laundering and terrorist financing 2019
28
Q

Report suspicious behavior

A

complete suspicious activity report and inform money laundering officer and national crime agency. Must not inform invidual that they have been reported

29
Q
  1. What does COSH stand for?
A

Control of substances hazardous to health

30
Q
  1. What are the 6 steps to risk assessment
A

Identify the hazard, decide who might be harmed by it, evaluate risk and precautions, make written documents and implement, review and update, advise those affected

31
Q
  1. What is a profit and loss statement
A

Shows income and expenditure of a company and resulting profit and loss