Case Study Flashcards
How did you demonstrate value for money?
Value for money arises from when expenditure is deemed to solve a problem. The problem at hand was having a neutral space for the individual organisations within the Euston Partnership to work together. Beyond this, quality was required to meet the price, maximum use was required and it was win-win (HS2 could get the funding for the space, and the end users a space to use).
How did you decide on this contract? Were there any alternatives?
How did select the contractors from a framework?
Would you ever approach a contractor ahead of sending the tender documents?
How might you establish the contractors capabilities before selecting them to be included in the tender process?
How were delay damages calculated?
If a client came to you and requested £50k a week in delay damages, what would you advise?
What is a suitable turning circle and passage dimension?
1500mm
What height should kitchen units be under Part M?
Wall units should be fitted 350mm above standard worktop height
What specific considerations would you give if installing a recess under a sink?
Ensuring it is 700mm high and insulated.
How else was accessibility considered in the CAT B fit out?
Fridge installed under the counter, slip resistance was excellent, the LRV of walls and floor was considered for contrast.
What is the process of a compensation event?
Were the works already complete, why would the contactor wait until the furniture is delivered to certify completion?
What would an accessible door width be?
External - 1000mm
Internal - depending on width of approach and if the building is existing or not 750mm - 825mm
Did you consider how the cupboard doors are operated?
The client preferred the spec of the doors installed as the handles were low which was more accessible for those in chairs. I advised this may present challenges for people with poor dexterity, to which they said they would instruct a replacement / installation of larger handles if the need arose.
What light reflectance value did you consider?
Under BS8300, I ensured the floor finishes and the wall finishes had a points difference of 30 or more. In the teapoint this was 53 vs 85. It was 20 vs 85 in the carpeted areas.
You mention the Press Conference. What was the Press Conference about?
The press conference was discussing the unveiling of the New Euston station design.
You mention entering the early warning into the early warning register, why did you do that?
Under NEC 3, it is actually known as the risk register but referred here by its new name early warning register for clarity. I