CAPM: Planning Process Group Flashcards
1
Q
Q: How many project management processes belong to the planning Process Group?
A
- 24
2
Q
Q: The planning process group contains which of the following?
A
- The project management processes that occur when the project is being organized and prepared.
3
Q
Q: What is the key benefit of the planning process group?
A
- Defines the course of action to successfully complete the project or phase
4
Q
Q: Select the best description of the planning process group.
A
- The process(es) required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.
5
Q
Q: Which of the following project management processes do not belong to the planning process group?
A
- Identify stakeholders