CAPM: Manage Project Knowledge Flashcards
1
Q
Q: What is the key benefit of managing project knowledge?
A
- Prior knowledge is leveraged to improve outcomes and knowledge created is available to support future projects.
2
Q
Q: Which document is used to improve the performance of the project and avoid repeating mistakes?
A
- Lessons learned register
3
Q
Q: All of the following are inputs to manage project knowledge EXCEPT:
A
- Knowledge management
4
Q
Q: Lessons learned documentation generally includes all of the following EXCEPT:
A
- Other types of lessons learned about communications management
5
Q
Q: Leveraging prior knowledge to improve outcomes and making knowledge created available for future projects is a key benefit of which of the following project integration management processes?
A
- Manage project knowledge
6
Q
Q: Which of the following best describes the overall purpose of the lessons learned register?
A
- To improve the performance of the project and avoid repeating mistakes
7
Q
Q: Which of the following are examples of explicit knowledge?
A
- Records