Capital Cost Estimating In Process Design Flashcards

1
Q

Define capital investment

A

The sum of money supplied in order to implement a design project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List some things included in the capital investment

A

Design work

Purchasing and installing of equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Capital investment can be further classified into…

A

…working capital and fixed capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define fixed capital

A

Total cost of the plant up to the point when the plant is ready for startup. It is a once-off cost that is not recovered at the end of the projects life other than the scrap value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Fixed capital cost includes…

A
  • Design and other engineering and construction supervision
  • All items of equipment and their installation
  • All piping instrumentation and control systems
  • Building and structures
  • Auxiliary facilities
  • Cost of development of the project
  • Lab experiments
  • Electrical equipment and materials
  • Yard improvements
  • Property costs
  • Construction expenses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define working capital

A

The additional investment needed, over and above the fixed capital, to start the plant up and operate it to the point when income is earned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Working capital includes…

A
  • Start-up
  • Initial catalyst charges
  • Raw materials and intermediates in the process
  • Finished product inventories
  • Funds to cover outstanding accounts from customers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Working capital consists of what three primary assets?

A
  1. Inventories
  2. Accounts receivable
  3. Cash resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is working capital funded

A
  • trade creditors
  • interest bearing debt
  • bank overdrafts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The accuracy of a capital cost estimate depends on which three factors

A
  • The amount of design detail available
  • The accuracy of the cost available
  • The time spent on preparing the estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

List the five types capital cost estimates can be classified into according to their accuracy and purpose

A
  • Order-of-magnitude estimate (ratio estimate) - based on similar previous cost data (+30% accuracy)
  • Study estimate (factored estimate) - based on the knowledge of major item of equipment (up to 30%)
  • Preliminary estimate (budget estimate) - based on sufficient data (up to 20%)
  • Definitive estimate (project control estimate) - based on almost complete data but before completion of drawings and specifications (10%)
  • Detailed estimate (contractors estimate) - based on complete engineering drawings, specifications and site surveys (within 5%)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define cost escalation (inflation)

A

The situation where prices of goods and services increase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define cost indices

A

They relate present cost to past costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are cost indexes based on

A

Data for labour, material and energy costs published in government statistical digests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

List the factors affecting investment and production costs

A
  • Sources of equipment (cost savings can be made if idle or 2nd hand equipment can be used - otherwise several quotations should be obtained for new equipment)
  • Price fluctuations (price levels for both equipment and man-hours increase)
  • Company policies (Policies of individual companies have a direct effect on cost)
  • Operating time and rate of production
  • Governmental policies (policies on waste disposal, water usage and taxes)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Name some direct cost items

A
  • Equipment erection, including foundations and minor structural work
  • Piping, including insulation and piping
  • Electrical, power and lighting
  • Instruments, local and control room
  • Process buildings and structures
  • Ancillary buildings
  • Storage, raw materials and finished product
  • Utilities, provision of plant for steam, water, air, fire fighting services
  • Site and site preparation
17
Q

Name some indirect cost factors

A
  • design and engineering cost
  • contractors fees
  • contingency allowance
18
Q

List some major pieces of equipment defined in the factorial method

A

Storage tanks, reaction vessels, columns, heat exchangers and others