Capital Budgeting Flashcards

1
Q

Steps of cost-benefit analysis

A
  1. Specify alternative projects
  2. decide whos beneftis and costs count
  3. Identify all relevant costs and benefits of the alternative projects
  4. predict quantitatively (in $) costs and benefits over the life of the project
  5. Discount benefits and costs to obtain present values
  6. Compute the net present value (NPV) of each alternative
  7. Perform sensitiviy analysis
  8. Make recommendations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discount rate/rate of interest/minimum acceptable rate of return (MAR) allows us to…

A

bridge time in comparing values.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Simple discount rate formula

A

PV=FV/(1+n)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Real vs Nominal dollars

A

Nominal dollars are actual price of a good or service.

Real dollars are net of inflation price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Consumer Price Index CPI

A
  • measures inflation

- calculated by price levels increase or decrease for households

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Real price formula

A

RP= (Nominal price/price index)* Base of price index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Real price calculation e.g
Base CPI (of 2011)=100
1980: $35, CPI=26.8
2014: $100, CPI=105.2
A

1980: 35/26.8*100 =

2014 100/105.2*100=

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Real discount rate formula

A

r=n-p (n= nominal interest rate, p= inflation rate)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PV of a single sum formula

A

V0=Vn/(1+r)^n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PV of perpetual annuity

A

V0=a/r

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PV of perpetual periodic series

A

V0=Vt/((1+r)^t -1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
PV e.g:
Revenue per t years (Vt)=$100,000/ha
Planting Costs(Cp)=$1000/ha
Annual management costs (m)=$100/ha/y
r=8%
t= 40y
A

Vo=(Vt-Cp/((q+r)^t-1))-(m/r)-Cp

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a discount rate

A

opportunity cost of capital (i.e where else could you be putting your money)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NPV

A

PV of revenues minus PV of costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

NPV decision rule

A
  • result >= 0, project is desirable (NPV of 0 = no return)

- if comparing projects, highest NPV is most desirable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Internal rate of return (IRR)

A

the discount rate at which the present value of the revenues equals the present value of the costs
- discount rate where NPV = 0

17
Q

B/C ratio

A

present value of the benefits divided by present value of the costs
- project is acceptable if B/C = 1 (same as NPV=0)

18
Q

Payback period

A
  • time it takes to recover invested capital
  • shorter period desirable
  • disadvanage: doesn’t consider NPV or IRR
19
Q

Challenges to ranking projects:

A
  • assumption of reinvestment of income earned before end of project at the IRR of the project
  • NPV criterion can hide amount of capital required in a project (e.g $1M investment @IRR=6.5 vs $10k inv. @IRR=20% and MAR is ^% then NPV of inv. 1 is higher)
  • Unequal investment durations: to compare, put on same time period (i.e 10y project x3 to match 30y project)