CA Services Flashcards
G704-DB
Certificate of Substantial Completion for OWNER to fill out because owner takes on that responsibility in DB
G732
Application and Certificate for Payment - CM Adviser Edition anticipates that the architect and the construction
manager-adviser may certify a different amount than that applied for, with each initializing the figures that have been changed and providing explanations accordingly.
The architect’s construction phase services are typically
described in these documents.
- Owner-Architect Agreement
- General Conditions
- Supplementary General Conditions
- Specifications Division 1
G612
Owner’s Instructions to the Architect Regarding the Construction Contract, Insurance and Bonds, and Bidding Procedures is a questionnaire used to obtain information from the owner necessary to arrive at a construction contract through the bidding process.
D200
Project Checklist identifies tasks and data necessary to fulfill assigned project responsibilities. It can also serve as a permanent record of owner, contractor, and architect decisions.
G716
RFI
Project Authority Matrix
Can be found in A201. Designates if O, A or C must approve contract elements.
Purpose of architect’s site visits
The purpose of site visits is to observe the progress and quality of the work, determine its conformance to the design, and report findings to the owner.
G711
Architect’s Field Report
G702
Application and Certificate for Payment. GC shall submit itemized application for payment to architect at least 10 days prior to date established for progress payments in accordance with schedule of values. Needs to be notarized, contain supporting data and reflect retainage. Can include payment for work authorized by CCD. Architect has 7 days to review/approve. The owner could have as little as 3 days to make payment. Certificate for payment does not constitute acceptance of Work not in accordance with CDs. Look for progress and quality.
G703
Continuation Sheet / Schedule of Values: Required for stipulated sum or GMP contracts
G701
Change Order: prepared by the architect, signed by the opener and contractor stating their agreement on:
- Change in the work
- Change in contract sum, if any
- Change in contract time, if any
G714
Construction Change Directive: prepared by the architect, signed by the owner and architect directing agreement on on contract time, sum or both. Once a contractor signs it, it will become a change order.
G710
Architect’s Supplemental Instruction: used for minor change in the work. Only needs architect’s approval. Architect submits in writing and if contractor thinks there is a change in contract sum or time, he should inform the team and not proceed until approved. If they proceed with the work anyway, they waive the right to the change in time/money.
Inspections vs observations and certification of work
All site visits are just observations except for inspections for substantial completion and final completion. Substantial completion is certified by the architect, and final completion is documented only by the architect’s issuance of the final certificate for payment. The certification of the final contractor’s application for payment is not a certification of final completion because the architect is not responsible for the completion or conformance of the work.
G704
Certificate of Substantial Completion
1 Year Walk Through
Required by B101 if requested and without compensation. Review warranty issues and gather information on how building is performing.
Retaining project-related documents
Unless required for longer period in contract, documents are usually kept for period of statutes governing claims. 15 years is common. Keep longer for repeat clients/future work.
Post-construction additional services
Lists found in B101 and D200: Post Occ Eval, construction as-builts, commissioning, LEED, FFE, Interior Design, warranty review, move-in assistance, energy analysis
Contracts for post-construction additional services
2 ways: G802, Amendment to the Professional Services Agreement adds services to original agreement (statute of limitations has already begun). B101 creates another contract and statutes timeframe begins again.
Commissioning: What, who and why?
QA process and oversight for a successful turnover of a new building. Hired by owner to verify the building is delivered and designed per the owner’s objectives. Benefits: energy savings, cost less to operate, reduced change orders, longer equipment life, improved indoor environment, staff trained in operations. Required for all LEED projects.
Unit prices
Stated in the bids and provide a price per unit fo materials and/or services. They offer the Architect and Owner a comparable means of measurement to use in comparing bids.
Reviewing consultant submittals
Architect can review for coordination but not stamp. Markups should be visually separate from consultant’s.
Informational submittals
Not reviewed by architect, only submitted to Architect to inform them that they have met the contractual submittal obligations. Includes: Coordination drawings and performance-based engineering calculations.