Building procurement Flashcards
What are the 4 main types of tendering?
1 - Open tender
2 - Selective tender
3 - Negotiated tender
4 - Single-stage and two-stage tendering
What different forms of procurement are appropriate for a £12million office development and what would influence the choice?
Traditional, D&B, Management (MC & CM), Collaborative
Choice effected by:
- Attitudes to risk
- Complexity of the project
- Time
- Cost certainty required
- Design control
- Quality
How do architects duties vary in different types of building procurement routes/ contracts?
General contracting
Contract administrator acting for the client (agent: instructions, inspecting works etc) and independent adjudicator (claims, valuation etc)
Design and Build
Techincal co-ordination, production information
Management
Lead consultant and information co-ordination, design information, approval, etc
Under the JCT SBC16 form of building contract, what actions should the architect take when the Completion Date has passed and the works are not finished? What rights does the Employer have under the contract?
Issue a Non-Completion certificate; The Employer has the right to deduct LD’s (Liquidated damages) provided correct notification procedures are followed
What are the different methods of dispute resolution?
Negotiation, Conciliation, Mediation, Adjudication, Arbitration and Litigation
What are the duties of the contract administrator in a standard form of building contract?
To act impartially with respect to both parties to the contract.
Issuing: o Contract Administrator Instructions o Variations o Interim certificates o Certificates of non-completion, extensions of time, practical completion, final certificate.
Assessing Notices by both parties
Explain what is meant by a Contract Administrator under a traditional building contract carrying out a dual-role?
Under a traditional contract a Contract Administrator carrying out a dual role is also the Architect. As well as their duties as architect to inspect work on site and act for the employers interest, they are also required to take on an impartial role to administer the contract between the Contractor and the employer.
If a Domestic Client gives written notice to ‘pay less’ to the Architect than the Notified Sum invoiced, what additional information must the Client supply?
The client must provide a letter outlining which terms of the appointment contract the Architect has not met to justify the retention of fees. This is why the scope of services and brief and fees should be clearly defined at appointment.
Under a JCT form of Contract, when is a building Practically Complete?
The building is practically complete when all elements defined in the contract documents have been completed and the patent defects have been rectified by the contractor. PC can also be issued when it would generally be perceived that the building is fit for the client to take possession, but there may be some ‘de minimus’ elements of the work that still need to be carried out that would not get in the way of the client using the building.
Give your definition of practical completion certificate
A certificate issued by the CA when construciton has been finalised and possession of the site is transferred from the contractor to the Client.
Design and Build. Give your definition of the following:
1) Consultant switch
2) Novation ab initio
1) In novation, when agreement between a Consultant and a Client is terminated and a new one is signed with the contractor.
2) ‘Ab inition’ means ‘from beginning.’ When consultants are novated and their liability to the contractor includes services to the beginning of the involvement in the project
Give five questions to ask a contractor you hope to use for the construction of your own house?
Do they have relevant experience for the type of work?
Do they have insurance provisions?
What is the cost of works?
What is the programme?
Recommendations for specialist sub-contractors?
What is the difference between sectional completion and partial possession?
‘Sectional Completion’ is an allowance for different completion dates and possession for different portions of the works and must be defined in the building contract. ‘Partial Possession’ allows for possession of a portion of the site and may be done post contract.
Explain what is meant by a relevant event
A relevant event is an event that causes a delay to the completion date, which is caused by the client, or a neutral event not caused by either party. The contract should set out what constitutes a relevant event. Relevant events entitle the contractor to claim an extension of time; that is for the completion date to be moved.
NOTE: A relevant event does not necessarily entitle the contractor to claim loss and expense. To claim loss and expense, a relevant matter must have occurred.
Relevant events might include:
- Variations.
- Exceptionally adverse weather.
- Civil commotion or terrorism.
- Failure to provide information.
- Delay on the part of a nominated sub-contractor.
- Statutory undertaker’s work.
- Delay in giving the contractor possession of the site.
- Force majeure (such as a war or an epidemic).
- Loss from a specified peril such as flood.
- The supply of materials and goods by the client.
- National strikes.
- Changes in statutory requirements.
- Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
Explain what is meant by a relevant matter
A relevant matter is a matter for which the client is responsible that materially effects the progress of the works. This enables the contractor to claim direct loss and / or expense that has been incurred.
Relevant matters might include:
- Failure to give the contractor possession of the site.
- Failure to give the contractor access to and from the site.
- Delays in receiving instructions.
- Opening up works or testing works that then prove to have been carried out in accordance with the contract.
- Discrepancies in the contract documents.
- Disruption caused by works being carried out by the client.
- Failure by the client to supply goods or materials.
- Instructions relating to variations and expenditure of provisional sums.
- Inaccurate forecasting of works described by approximate quantities.
- Issues relating to CDM.