builder advanced ch2 Flashcards
What is the official contract drawing that you will mark
on during construction to show the actual as-built conditions?
Red-Lined
When a construction project is completed, what type of drawing must be submitted to ROICC?
As-Built
What type of plan shows the spot where a building is to be placed on a piece of land?
Site
To find the size and placement of reinforcing steel in the grade beam for a building, you should look in what main division of the drawing?
Structural
Which of the following divisions should contain the environmental pollution controls?
Civil
Specifications from which of the following sources, combined with drawings, define the project in detail and show exactly how it is to be constructed?
Project specifications
True/False
Whenever there is conflicting information information between the drawings and project specs, the specifications take precedence over the drawings.
True
The Construction Standards Institute (CSI) has organized the format of specification into 16 construction divisions, but NAVFAC has added a 17th division.
Expeditionary structures
True/False
in most NCF projects, construction activities should not be less than six days in duration.
False
What section of the project package contains the Bill of Materials.
Three
The work schedule of a battalion for one person per week is based on an average of how many hours?
55
In an NMCB, what is the normal duration of a workday, in hours, to and from the job site?
9
NAVFAC P-405, Seabee Planner’s and Estimator’s Handbook defines a man-day as how many hours per day?
8
What type of estimates are the basis for purchasing materials, determining equipment, and determining manpower requirements?
Activity
Master activities are usually assigned to the projects by what authority?
NCRs
Which of the following activities is NOT an activity that would be listed on a Master Activities List for a typical building project?
Paint
What NAVFAC publication lists the number of man-hours to accomplish one unit of work?
P-405
(TRUE OR FALSE) The man-day capability equation is used to calculate the duration of a construction activity.
True
For planning purposes, what authority assigns an availability factor to an NMCB?
Naval Construction Brigade
Which of the following information is NOT documented on Construction Activity Summary sheets?
PRCP skills