Bu basic CH4 Flashcards
1
Q
- What is the process of determining requirements and devising and developing methods and action for construction a project? (Page 4-4)
A
planning
2
Q
- What is the process of determining the amount and type of work to be performed, quality and the quantities of material, equipment, and labor required? (Page 4-4)
A
estimating
3
Q
- Who is a person who evaluates the requirements of a task? (Page 4-4)
A
estimator
4
Q
- What is the process of determining when an action must be taken and when material, equipment, and manpower and required? (Page 4-5d
A
schedulling
5
Q
- The four basic types of schedules include progress, material, equipment, and what else? (Page 4-5)
A
manpower
6
Q
- What are your main basis for defining the required activities for measuring the quantities of material?
A
construction drawings
7
Q
- What are used as a basis for purchasing materials, determining equipment, and determining manpower requirements? (Page 4-13)
A
quantity estimates
8
Q
- A typical NMCB project might have between fifteen and how many construction activities? (Page 4-15)
A
50
9
Q
- What is a clearly definable quantity of work? (Page 4-20)
A
activity
10
Q
- What are used to procure construction material and to determine whether sufficient material is available to construct or complete a project? (Page 4-20)
A
material estimates
11
Q
- What percent of the posted speed limit does equipment speed usually average? (Page 4-24)
A
40-56%
12
Q
- What part of the Naval Mobile Construction Battalion (NMCB) contains specific information on the quantities and characteristics of construction equipment available to the NMCBs? (Page 4-27)
A
table of allowance (TOA)
13
Q
- According to NAVFAC P-437 a man day is equivalent to a how many hour day for contingency operations? (Page 4-27)
A
10
14
Q
- What is considered productive labor that does not contribute directly or indirectly to the product? (Page 4-27)
A
overhead labor
15
Q
- What are the two types of labor estimates? (Page 4-27)
A
preliminary detailed
16
Q
- A good preliminary estimate varies less than what percent from the detailed estimate? (Page 4-28)
A
15%
17
Q
- What represents any sequencing of priorities amount activities that form a project? (Page 4-34)
A
network
18
Q
- What are intermediate goals within a network? (Page 4-35)
A
milestones
19
Q
- What is an activity within the network that has zero float time? (Page 4-35)
A
critical activities
20
Q
- What is the accumulative time span in which the completion of all activities may occur and not delay the termination date of the project referred to as? (Page 4-41)
A
total float
21
Q
- What is the time span in which the completion of an activity may occur and not delay the finish of the project or the start of a successor activity referred to as? (Page 4-41)
A
free float