breach and remedies Flashcards
discharge of contract
usually a contact discharges because both parties have done what they have gareed in teh contract.
if they haven’t done what they said they would tehn thi scan be discharged by breach
however not all contracts that have been breached will be discharged.
discharge by performance
performance must be exact and complete
cutter v powell
cutter v powell
cutter agreed to work second mate on a voyage for a fixed fee. Cutter died near the end of his voyage. his wife sued for a proportion of his fee. she was entilited to nothing as he agreed to work his the entire voyage and did not due to his death.
due to his death he did not carry out his full performance was not exact and complete = no payment
Re Moore ad Co Ltd
the total number of tins were correct, but he number of tins in each carton was incorrect so the goods did not correspond with the description of t contract
not exact and not complete so no payment needs to b made.
discharge by performance has different ways it can be used
this is because the rule of discharge by performance being only when all aspects of the contact have completed is to harsh.
divisible contracts
substantial performance
prevention of full performance
acceptance of part performance
divisible contract
if the contract has seperate parts to it, then non-completion of one part. not a breach of a whole contract
3/4 of a contract
divisible contract
in the case cutter v powell if the contract descibed an hourly wage or per pay a day then the contract would have been divisible
Divisible contract key case
ritchie v Atkinson 1808
a ship owner agreed to carry a cargo at an agreed rate per ton. he carried only part of the cargo the ship owner was entilited to be paid for the part of the cargo he had carried out at the agreed price per ton. but he was liable in damages for a breach of contract for not carrying out he whole cargo.
substantial performance - very subjective
if what has been expecte d has substantially been done, under teh contract then teh doctrine of substantial perforance may apply.
if it does paply there will be a payment fr teh maout of work you bhave done.
this is only appliciable mto divisble contracts, not contracts were teh entire agreement is one singlem money transaction
Substantial performace key case
Dakin and Co v Lee 1916
buileders agreed to repair teh d premesies for 14500, they prformed teh contract completelty but there were 3 relativley 3 bad prformed areas.
these costs £80.
- courts decided that the contract hasd been substantially, if not performed. The fact the work was done badly di not mean it had not been performed at all.
- still completed the job - substantial - payment was made based on what they have done.
no rule to what amounts to substantial
instead, courts will subjectively at ths on a case by case basis
hoening v isaacs 1952
bolton v mahadeva 1972
Hoening v isaacs 1952
a decorater was contracted to decorate and furnish a room for £750. some of the furniture was defetive but could be repaired for £55. courts decideed that the contract was substantially completed o financial basis. decorater was paid on a qantum meruit basis.
- has substantially peformed shows subjectivness
quantum merit basis
young v thames
courts will award as much as it is worth
- contractor was contracted to resurface a car park, overall did job but small deects. contractor was entilted t te contract due to the contcat sayijg less the saving thst he had done buy buying cheaper ,aterials which means it was not hi fault.
bolton v mahadeva 1972
builder agreeed to install a central heating system for £500 however the installation was defective. repairs costs £170. court decided that the builder was entilted to nothhing as there had not been substantial performance of the contract.
legal principle - hasnt substantially peformed shows subjectivness.
prevention of full performance
prevents the other from carrying out their end of the contract, then the innocent party can still claim to be paid on a quantum meruit basis.