Blueprint Questions Flashcards
(These are some actual questions on the exam. They are somewhat vague but it would not hurt to study them. It is better to figure or look up in plans yourself but these are good to remember if you happen to run out of time) There are 4 sets of Drawings and a Figure Booklet. The drawings are listed below: 1 – 3 Story Parking Deck 2 – 6 Story Parking Deck 3 – 5 Story Mixed – Use Building 4 – Industrial Building Note: The 3 Story Parking Deck and the 6 Story Parking Deck a (112 cards)
– 6 Story Parking Deck – How many rooms receive a ceramic tile floor?
Answer: 1 Room
Industrial Building – How many CMU block are there in the dumpster area?
Answer: 467 CMU block
– 5 Story Mixed – Use Building – How many roof drains are there?
Answer: 12 roof drains Note: The Parking Decks have 2 roof drains
`– 5 Story Mixed-Use Building – How many linear feet of aluminum frame on the floor?
Answer: 126 feet
Industrial Drawing – The west loading dock wall has a 1 percent slope and is 50 linear feet long. What is the total amount of slope?
Answer: 6 inches
Note: 50 feet x .01 = .50 or 6 inches
6 – 6 Story Parking Deck – Need to look on the Structural and Architectural Drawing for the size of the footings. They will have you figure footing quantities or just the sizes, whichever question that they ask.
Typical interior spread footing is 16 inches wide x 12 inches deep
Interior spot footing is 12 feet x 12 feet x 24 inches deep – Quantity is 14
Perimeter or exterior footings are 8 feet x 8 feet x 16 inches deep – Quantity is 36
Industrial Drawing – How many linear feet of edge metal are required on the 4 foot canopy at the back of the building?
Answer: 154 feet 2 inches (do not count the 4 foot sides on each end)
8 – Industrial Drawing – Loading dock has a 50’ x 50’ concrete pad. If there is a 1% fall, how much would the concrete fall? Probably same as question # 5.
Answer: 6 inches
Note: 50’ x .01 = .5 of a foot or 6 inches
9 – Industrial Drawing – There is a 6 inch concrete pad 60’ x 50’ of lightweight concrete with fiber mesh. The concrete cost $ 115.00 per yard and the fiber mesh is an additional $ 5.00 per yard. How much extra cost is for the fiber mesh?
Answer: $ 278.78
Cost of concrete has no bearing on question, just the fiber mesh cost on 55.56 cubic yards of concrete
10 – Industrial Drawing – How many 5 inch columns are there in the tower crane base?
Answer: 10 columns
Note: There are 5 on each footing.
11 – 5 Story Mixed – Use Building – What floor finish does the 2nd story bathroom receive?
Answer: Tile
Note: There are 2 different room finishes on this drawing, make sure that you have the correct room number to find correct finish schedule.
12 – 6 Story Parking Deck – What is the average exterior wall height?
Answer: 42 inches
13 – 6 Story Parking Deck – How many drains are there on the roof?
Answer: 2 roof drains
14 – 5 Story Mixed – Use Building – How many cubic yards of concrete is required for Stairway # 1?
Answer: 48 cubic yards
15 – 5 Story Mixed – Use Building – How many linear feet of handrail are needed for the 3rd floor balcony and the open area?
Answer: 309 linear feet
16 – 5 Story Mixed – Use Building – You are allowed a $ 200.00 allowance for signs on this project and each sign is valued at $ 25.00 each. Which of the below is true?
Answer: $ 75.00 needs to be returned (there were only 5 signs at $25.00 each)
17 – 5 Story Mixed – Use Building – What is the height of the ceiling in the Courtyard Area?
Answer: 36 feet
18 – Industrial Building – How much concrete is needed for the footing on each side of the overhead crane?
Answer: Less than 1,000 cubic yards
Note: The concrete needed is 110 cubic yards, but the answer given that best works is less than 1,000 cubic yards.
19 – 6 Story Parking Deck – How many pieces of 8 inch ceramic tile will be required for the 42 inch high wall around column line 7?
Answer: 381 pieces of ceramic tile
20 – 5 Story Mixed – Use Building – How many double door openings are there in the store fronts?
Answer: 7 double door openings
21 – Industrial Building – A concrete sub is paid $ 50.00 per cubic yard to place the concrete in freezer slab on grade. How much is to be paid to the sub-contractor/
Answer: $ 1,463.44 (use the closest answer)
22 – Industrial Building – On the east and west side of the building, how many cells of concrete block need to be filled including the corners?
Answer: 40 cells
23 – 6 Story Parking Deck – How many future tenant rooms are required to have the concrete floors sealed?
Answer: 7 rooms
24 – 6 Story Parking Deck – What is the minimum required reinforcing steel for the interior wall footings?
Answer: 2 continuous # 5 bars