Batch Process Flashcards

1
Q

What is a batch process?

A

A batch process is a type of production in which units are produced in batches instead of one by one (individually).

Batch processes and setup go hand in hand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is setup (time)?

A

Setup time is by PER BATCH basis.

In this module, setup time is fixed. It is a constant value in this module.

Setup time and batch size interacts in such a way as to reduce the process capacity.

Also known as change over time or switch over time.

Setup time is required to change production from one type of product to another.

During this change, the time used to complete this activity does not depend directly on the number of units produce.

For example: Making clothes. We need to change the dye to obtain clothes of different colors. This time used to change the dye is the setup time.

Batch processes and setup go hand in hand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a batch size?

A

This refers to the number of flow units on each tray going into the oven.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a production cycle?

A

A repeating sequence of produced units that can include set up time, production time and idle time.

It is the total sum of when the process starts and when the whole process ends, includes the fixed cost time (setup time).

Production time is how much time the flow unit is being worked on. Different from production cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is capacity?

A

Capacity = (# of units processed) / (total time taken)
= b / time for a production cycle

, where b = batch size.

Time for a production cycle = b x unit processing time + setup time.

  • Setup time must add every changes there is in the process.
  • Unit processing time needs to include the unit processing time of all the different processes in the batch process. If there are two activities in the production cycle, the total unit processing time will be the sum of the processing time of both the activities.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a batch?

A

The group of flow units(cookies) on a tray that is going into the oven to be cook.

In this module, we are assuming that at any point of time, no flow units will be taken out of that group until the whole batch is processed.

When batch is greater than 1, it makes the flow time of the flow unit longer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What affects the process capacity?

A
  1. Batch size
  2. Setup time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Setup and set down time. How do we read set down time?

A

Set down time is considered as part of setup time as it is required before the production can continue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Cml?

A

The capacity of a resource. This is a rate. If capacity is fixed, the processing time will be fixed at 1/Cml.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can a process capacity changed when the capacity of resources are fixed?

A

It is because:
1. Setup time.
2. Batch size.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Capacity with Setup and Batch = Cbs.

A

We need to assume that the setup is non zero and batch size is greater than 1.
Batch size of one is basically the flow unit itself.

Cbs
= Total units processed / Total time taken
= B / (S + pB)

1 cycle = S + pB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If setup is 0, what happens?

A

When there is no setup time, and using the formula of B / (S + pB), we can recover Cml = B / pB. -> B = batch size

With the presence of setup time, it will affect the process.

Setup time is always a bad thing as it always reduces the capacity, Cbs.

When setup is 0, we achieve the ideal situation.

Reducing setup time is always the right option to help improve Cbs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In the presence of set up time, is large batch size better or small batch size better?

A

When there is setup time, we will prefer the batch size to be larger by theory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When there is very large batching, what can happen?

A

When batch size goes infinite, Cbs = 1 / p = Cml.

We can recover the original machine-label capacity.

Large batch size is a good thing. (It will be generally better than reducing the setup time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How can one increase process capacity?

A

Increase the batch size. Reducing setup time can be more difficult to achieve than increase the batch size. Hence, choose increasing the batch size is better than reducing the setup time.

Increasing the batch size is the first option. If that is not possible, then we choose reduce the setup time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does batch size of 1 mean?

A

The entire flow unit suffers setup time.

When batch size is 1, the question could mean that your Cbs is the same as Cml.

Batch size of 1 is as good as S = 0.

How then can we interpret the question that did not say batch size of 1 as having no setup time?
- Scan the question that mention any setup activity. If no words like “warmup” , “preparing” etc, then we are most likely talking about Cml.

16
Q

What does no batching mean?

A

It means that there is no set up time incurred.

Cbs = Cml.

17
Q

How can we increase Capacity, Cbs?

A
  1. Reduce the setup time (as much as possible)
  2. Increase the batch size.
18
Q

What is target capacity?

A

What capacity do I want to achieve.

If my setup time cannot be change, what is the new batch size I need to achieve?

My production time cannot be changed because of Cml.

B = (Ctarget x S) / (1 - (Ctarget x p))

19
Q

What is the relationship between batch size and flow time?

A

When batch size increase, flow time also increases.

Each flow unit needs an equal amount of time to be processed. Hence, the more flow units there are, the long time is required to be processed.

20
Q

What is Work in Progress?

A

This refers to inventory = Flow time x Flow rate (Little’s law)

21
Q

Utilization (with batch size and setup time involved

A