Ballast RM - Delivery Of Service Flashcards

1
Q

Accepting a project

A

Evaluate: budget, reputation
Agreement: scope, fee, others in contract
May predesign and construction schedule to see feasibility and fee

Seeking to interfere with an existing contractual relationship is not ethical, maybe illegal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Seeking a delivery method

Factors: cost, schedule, project scope, building quality and risk.

A

Traditional: owner to architect as agency, representing clients interest; owner to contractor, with fixed fee and time. Separate contracts with each.

More recent: one entity to design and build.

Cost: Design-bid-build, lowest cost but risk from contractor

Schedule: fast track method (“overlapping tasks”from internet) with multiple prime contracts and a construction manager as constructor

Scope: when a project has many unknowns, use cost plus fixed fee from the contractor with or without guaranteed max.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Delivery Methods:

Design bid build

Construction manager as adviser
Construction manager as constructor
Design Build
Design Assist Contracting
Integrated Project Delivery
A

DBD: architect designs finished, provides CD and specs; bidding or negotiating a contractor( fixed price, no savings). Not suitable for quick project or extended design and construction.

Advantages:
Linear and simple process thru;
Straightforward coordination between.

Chances of contractor underestimating to give competitive bid are high;
The bid docs need to be redrawn and detailed well for accurate bids.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Delivery method-CMa

A

CMa: construction contractor or third party hired before design is finished; outside of architects contract; no competitive bidding, higher cost; more complicated management structure.

Construction Cost: 1. Fixed price method, owner not sharing if any savings; 2. Cost plus fee with a guaranteed max price, client receiving if any savings; 3. Cost plus fee with no GMP.

Fast track common when CM is in: construction starts before design completed because documents issued in stages.

CM joint with architects on CA

CMa is not contractor, no direct cost control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Delivery method - CMc(constructor)

A

Part of contracting firm, single agreement on construction management and construction services.

I Cost plus fee with or without GMP.
No stipulated sum option.

Architects CA advising and consulting responsibility begins: owner accepts GMP, owner approves control estimate, owner issues a notice to proceed to CMc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Design method - Design-Build

A

Owner contracts with one entity.

Often construction contractor with independent architect and engineer as consultant.

Less commonly, architect leads construction contractor and engineer as subcontractors to architect.

Or design-build entity with in-house design and construction.

Or design firm and construction firm do a joint venture separate from the firms.

State may limit on public works.

Fast time and low cost, single source responsibility; owner less control in design and construction.

Owner criteria - pre-design and proposed contract sum (fixed price) - Agreement

Owner’s duty: provide criteria, review and approve changes, site visit, rejecting non conforming work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Design-Build Variation: Bridging

A

When DB firm is best with manufacturer and subs to construct lowest cost.

Design-bid-build process and Design-build approach combined.

Owner hire architect/engineer(AE) as adviser/project manager to select design-build team. AE provide preliminary docs for bidding. AE review DB’s final but not legal responsible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Delivery method-

Design-assist Contracting

A

Subs in early design and CD phases to develop unique/complex portion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Design Method-

Integrated Project Delivery(IPD)

A

Multiple agreements VS one agreement in DB method

All on board since conceptualization phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three factors to for an architect to investigate are:

A

The adequacy of the client’s budget to meet the the architect’s fees and construction cost;
Credit rating of client;
Other designer’s and contractor’s opinion on the reliability of the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Design-build subcontractor handles

A

Bldg systems, including MEP and fire protection.