Back Filling Flashcards

1
Q

Piping must be covered with a minimum of inches of tempered Earth

A

12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Backfill must be free from

A

Discarded construction material and debris rocks broken concrete and Frozen chunks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Loose Earth must be carefully placed in the trench _” layers tampered in place

A

6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or false
Backfield must be placed evenly on both sides of the pipe and tampered to retain proper alignment

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly