B1, B2 & B3 Progress Test Flashcards

1
Q

List the correct sequence for preparing budgets:

A

Production Budget, Material purchases budget, budgeted income statement, budgeted balance sheet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An unfavorable direct labor efficiency variance could be cause by:

A

Unfavorable material usage variance. Poor quality materials could mean unfavorable material usage and cause inefficient labor usage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost of Equity Capital FORMULA

A
K = D/P + G
K = Cost of Equity Capital
D = Dividend next period
P = Stock Price
G = Growth %
How well did you know this?
1
Not at all
2
3
4
5
Perfectly