B1, B2 & B3 Progress Test Flashcards
1
Q
List the correct sequence for preparing budgets:
A
Production Budget, Material purchases budget, budgeted income statement, budgeted balance sheet.
2
Q
An unfavorable direct labor efficiency variance could be cause by:
A
Unfavorable material usage variance. Poor quality materials could mean unfavorable material usage and cause inefficient labor usage.
3
Q
Cost of Equity Capital FORMULA
A
K = D/P + G K = Cost of Equity Capital D = Dividend next period P = Stock Price G = Growth %