The elapsed time between obtaining the first and final portions of a composite sample shall not exceed _____minutes.
A. 2
B. 5
C. 10
D. 15

A

15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When it is necessary to wet sieve a concrete sample, wet sieving should be performed before the individual samples are combined into a composite sample.
(T or F)

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tests for slump, temperature, and air content shall all be started within _____ minute(s) after obtaining the final portion of the composite sample.
A. 1
B. 2
C. 5
D. 15

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Start molding strength test specimens within _____ minute(s) after fabricating the composite sample.
A. 1
B. 2
C. 5
D. 15

A

15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The sample of concrete should be
A. allowed to sit, undisturbed, in the container for 5 minutes before conducting any tests.
B. protected from the sun, wind, rapid evaporation, and contamination.
C. remixed with material re‐deposited in the container following the slump test.
D. remixed with additional water if the sample dries out during use.

A

protected from the sun, wind, rapid evaporation, and contamination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When test specimens are to be molded, the minimum sample size is _____ .
A. 1 ft^3
B. 2 ft^3
C. 0.5 ft^3
D. 5 ft^3

A

1 ft^3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The primary objective when sampling concrete is to
A. obtain a representative sample of concrete.
B. obtain 1 ft^3 of concrete.
C. minimize the contamination of the sample.
D. provide experience with we sieving a sample of concrete.

A

obtain a representative sample of concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When sampling from a revolving drum truck mixer, collect
A. one portion from anywhere in the batch.
B. all portions before water or admixtures have been added to the batch.
C. two or more portions at regular intervals from the middle of the batch.
D. all portions before placing any concrete in the forms.

A

two or more portions at regular intervals from the middle of the batch.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Wet sieving is performed
A. on all composite samples.
B. only when the Nominal Maximum Size (NMS) of the coarse aggregates is larger than 3 inches.
C. after the sampled portions are remixed onto a composite sample.
D. when the aggregate is larger than appropriate for a test.

A

when the aggregate is larger than appropriate for a test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When sampling from a paving mixer, it is permissible to place three shallow containers on the subgrade in
order to obtain the needed portions of concrete.
(T or F)

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Regulate the rate at which concrete is discharged from a revolving drum truck mixer by
A. adjusting the size of the gate opening.
B. changing the angle of the discharge chute.
C. placing a hand held dam in the chute.
D. adjusting the rate of revolution of the drum.

A

adjusting the rate of revolution of the drum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

After wet sieving a portion of a concrete sample, any aggregate retained on the sieve
A. shall be remixed with the remaining portion of the original sample.
B. shall be discarded.
C. should have any mortar on the particles wiped off and added to the sieved material.
D. is to be recombined with the sieved material before fabricating strength specimens.

A

Shall be discarded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Samples from a revolving drum truck mixer
A. should be of approximately equal volumes.
B. can be placed into the formwork after all tests have been completed.
C. should not be taken until all water and any admixtures have been added to the mixer.
D. should be take for each individual test performed on the fresh concrete.

A

should not be taken until all water and any admixtures have been added to the mixer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When sampling from a paving mixer, obtain _____ portions from the discharge pile.
A. at least 5
B. no more than 5
C. 3 to 5
D. 2 or more

A

at least 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sample concrete from a revolving drum truck mixer by
A. repeatedly passing a receptacle through the entire discharge stream.
B. completely diverting the discharge into a sample container.
C. neither A nor B.
D. either A or B

A

either A or B
A: repeatedly passing a receptacle through the entire discharge stream.
B: completely diverting the discharge into a sample container

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

After all portions of the composite sample have been obtained,
A. combine and remix the samples with a scoop or shovel for at least 3 minutes.
B. transport the samples to the place where tests are to be performed and specimens are to be molded.
C. Immediately begin conducting tests or molding specimens.
D. determine which tests are to be performed and the number of specimens to be molded.

A

transport the samples to the place where tests are to be performed and specimens are to be molded.