ARE CE #12 Flashcards
Who is responsible for errors and omissions on
submittals?
The Contractor is responsible for errors and omissions on submittals to the Architect.
What should the Contractor do if the Architect does not process a submittal in a
timely manner?
If no action has been taken by the Architect within the reasonable time, the Contractor will consider it to be approved. The Architect and Contractor must process
submittals within a reasonable time.
Are Shop Drawings part of the Contract
Documents?
No, shop drawings and submittals are not Contract Documents.
They show
how the Contractor intends to conform
to the Contract Documents.
Which AIA contract is A201?
General Conditions for Contract for Construction
Which AIA contract is G714?
Construction Change Directive
The Schedule of Values refers to…
Paying the contractor’s applications for payment.