ARE CE #11 Flashcards

1
Q

What is a “patent defect”?

A

A defect that would be “visible” in materials, equipment, or completed work by any reasonable observation or inspection.
Having a defect blocked
from view by a pile of trash does not
count as latent or hidden

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a “latent defect”?

A

A defect “hidden” in materials, equipment, or completed work and not readily apparent or capable of discovery
by reasonable observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s the difference between an RFP and an

RFQ?

A

An RFP includes any fees and costs, along with experience.
An RFQ asks for firms to submit their
relevant experience.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the AIA G706A – Contractor’s Affidavit Of Release of
Liens signify?

A

Affidavit that payrolls, bills for materials
and equipment, and other indebtedness have been paid or satisfied. It’s proof of release of all applicable liens – lien releases from subcontractors, vendors
and material suppliers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Let’s say you receive shop drawings for the steel work directly from the steel subcontractor. What should
you do?

A

Do nothing, send them back unchecked.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The term “at risk” in Construction Management at Risk,

means:

A

The contractor holds the trade contracts and takes the performance risk for
construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly