ARE 5.0: CE - Construction Observation Flashcards

1
Q

What other construction delivery method is most similar to the construction manager as constructor with regard to the many roles and responsibilities of the architect?

A

With regard to the many roles and responsibilities of the architect, this delivery method is similar to design-bid-build.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

During agency review, what is the architect’s role in an integrated project delivery project?

A

The architect’s role in this phase is limited to working with the permitting authority to show code compliance related to the building information model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of the architects site observation?

A

This is to observe the progress and quality of the work and keep the owner informed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who determines the number and frequency of the architect’s site observation visits?

A

The architect determines this during the construction administration phase at intervals appropriate to the stage of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who pays for additional field testing if the work does not conform with the contract documents?

A

The contractor must pay for this if the work is deficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the architect not responsible for during the construction of the project?

A

This team member is not required to perform exhaustive or continuous on-site inspections, or to be involved with means or methods of construction, or site safety.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

During construction, why must the architect speak directly to the general contractor and not to the subcontractors?

A

The architect is an agent of the owner and does not have a contractual relationship with this entity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are two situations in which completed work they have to be uncovered?

A

This may occur if work was covered contrary to the architect’s request or when no specific request was made by the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which document defines the lines of communication among the parties during construction administration?

A

AIA Document A201, “General Conditions of the Contract for Construction”, controls this during construction administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Through whom must the owner and general contractor communicate during construction administration?

A

These two parties must communicate through the architect unless stated otherwise in their agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who will pay for work to be uncovered when the work work was covered contrary to the architect’s request?

A

The contractor will pay to uncover work when this situation arises.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If uncovered work is determined to meet the project requirements, and the architect had not previously requested that it remain uncovered, who pays to uncover and replace the work?

A

The owner will pay to uncover and replace the work in this situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which document requires that certain portions of the work be subject to special inspections?

A

The International Building Code (IBC) requires special inspections of structural systems, prefabricated items, and certain materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who must evaluate and approve the Statement of Special Inspections?

A

The building official must review this document before special inspections can be incorporated into the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In which two forms of communication may field reports be distributed?

A

Hard copies and electronic formats may be used to distribute this document after a site observation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who is responsible for organizing a pre construction conference, and which parties are required to attend?

A

This meeting is organized by the architect and should be attended by the architect, owner, contractor’s personnel (project manager, account executive and superintendent), major sub contractors, and members of the design team (structural, electrical, civil and plumbing engineers, and so on, as required).

17
Q

How is “contract time” defined?

A

This period starts at the date established in the agreement and ends at substantial completion.

18
Q

Which party has the sole responsibility for the means of construction and the building technique?

A

According to the AIA Document A201, General Conditions of the Contract for Construction, these issues are the sole responsibility of the contractor.

19
Q

What two parties should each receive a copy of an architect’s field reports?

A

A copy of each of these architect’s reports must be provided to the owner and contractor.

20
Q

What should an architect do if he or she finds an unsafe condition on the project site?

A

If an architect observes such a condition on the project site, he or she must immediately notify the owner and the contractor.

21
Q

In AIA Document A201, General Conditions of the Contract for Construction, what term is given to the architect’s visit to the site?

A

In AIA Document A201, this is called a site observation or site visit.