ARE 5.0: CE - Administrative Procedures & Protocols Flashcards
Name two differences between a change order and a construction change directive.
A change order must be approved by the owner, architect and contractor, and all three parties must agree on the change in cost. The second procedure must only be approved by the owner and architect, and without all parties agreeing on the change in cost.
Which party produces a request for information (RFI)?
The contractor, owner, or architect can use this document to request additional information during the construction phase.
When is the contractor allowed to submit a request for payment of a construction cost directive to the owner on the application for payment?
This item can be submitted to the owner for payment upon agreement of the additional cost of the work by the contractor and owner, and completion of the work.
During the construction phase of the project, the contractor is required to make submittals to the architect. Name four types of submittals.
Four types of these are shop drawings, samples, product data, and documents related to sustainability issues.
Which document is used to record minor changes in the work?
This administrative action is recorded by the architect using AIA Document G710, Architect’s Supplemental Instructions.
If the work does not conform with the contract documents, who has the authority to reject the work?
The architect has the authority to take this action if work is not in compliance with the contract requirements.
The architect’s review of the shop drawings does not relieve the contractor of what?
The review of this by the architect does not relieve the contractor of conformance with the contract documents.
During the construction phase, who may make a claim on the project?
The owner or the contractor may take this action if they seek an adjustment to the time or payment of money or other relief from the terms of the contract.
In a shop drawing review, what are the similarities and differences between the “revise and resubmit” and “rejected” designations assigned by the architect?
Neither submittal complied with the contract documents as submitted. In the first, the contractor may provide additional information or make corrections and return the submittal to the architect for review. In the second, an item is unsuitable for use in the project and may not be resubmitted to the architect for review.
Describe the difference in roles between a mediator and an arbitrator.
In mediation, this person facilitates a discussion for the parties to reach their own settlement. In arbitration, this person allows the parties to submit their evidence and hears witness testimony before making a decision or ruling on the matter.
What is normally held from a progress payment until work is completed?
Retainage is normally withheld from this kind of payment.
Which party pays for additional non-conformance field testing?
This is the only type of field testing paid for by the contractor.
What information must be included on every progress payment application?
This application must include the value of the work completed to date and the value of any stored material.
Who pays for work rejected by the architect?
Under these circumstances, the additional work must be paid for by the contractor.
What fee method should be used when the owner has identified a specific set of services?
When the owner has done this, the architect can accurately estimate a stipulated sum contract.