ARE 5.0: CE - Administrative Procedures & Protocols Flashcards

1
Q

Name two differences between a change order and a construction change directive.

A

A change order must be approved by the owner, architect and contractor, and all three parties must agree on the change in cost. The second procedure must only be approved by the owner and architect, and without all parties agreeing on the change in cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which party produces a request for information (RFI)?

A

The contractor, owner, or architect can use this document to request additional information during the construction phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When is the contractor allowed to submit a request for payment of a construction cost directive to the owner on the application for payment?

A

This item can be submitted to the owner for payment upon agreement of the additional cost of the work by the contractor and owner, and completion of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

During the construction phase of the project, the contractor is required to make submittals to the architect. Name four types of submittals.

A

Four types of these are shop drawings, samples, product data, and documents related to sustainability issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which document is used to record minor changes in the work?

A

This administrative action is recorded by the architect using AIA Document G710, Architect’s Supplemental Instructions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If the work does not conform with the contract documents, who has the authority to reject the work?

A

The architect has the authority to take this action if work is not in compliance with the contract requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The architect’s review of the shop drawings does not relieve the contractor of what?

A

The review of this by the architect does not relieve the contractor of conformance with the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

During the construction phase, who may make a claim on the project?

A

The owner or the contractor may take this action if they seek an adjustment to the time or payment of money or other relief from the terms of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In a shop drawing review, what are the similarities and differences between the “revise and resubmit” and “rejected” designations assigned by the architect?

A

Neither submittal complied with the contract documents as submitted. In the first, the contractor may provide additional information or make corrections and return the submittal to the architect for review. In the second, an item is unsuitable for use in the project and may not be resubmitted to the architect for review.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe the difference in roles between a mediator and an arbitrator.

A

In mediation, this person facilitates a discussion for the parties to reach their own settlement. In arbitration, this person allows the parties to submit their evidence and hears witness testimony before making a decision or ruling on the matter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is normally held from a progress payment until work is completed?

A

Retainage is normally withheld from this kind of payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which party pays for additional non-conformance field testing?

A

This is the only type of field testing paid for by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What information must be included on every progress payment application?

A

This application must include the value of the work completed to date and the value of any stored material.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who pays for work rejected by the architect?

A

Under these circumstances, the additional work must be paid for by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What fee method should be used when the owner has identified a specific set of services?

A

When the owner has done this, the architect can accurately estimate a stipulated sum contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If an owner fails to substantially perform according to contract, what must an architect do to terminate the contract?

A

To take this action in regard to a contract with an owner, an architect must give the owner seven days’ written notice.

17
Q

What is a change order? Who prepares it?

A

This document is prepared by the architect and authorizes a revision to the original contract documents after the construction contract has been signed by the owner.

18
Q

When are shop drawings usually prepared?

A

These drawings, schedules, or diagrams are usually prepared after the subcontractor or material supplier has signed a contract with the general contractor.

19
Q

What is a mechanic’s lien?

A

This is a claim against a property made by a contractor, material supplier, or architect for an unpaid debt of the property owner.

20
Q

What type of drawings must the architect keep a log of?

A

Shop drawings require this type of record keeping.

21
Q

What is the advantage to the owner of using a construction change directive?

A

This document gives the owner a way to order changes in the work before agreeing to an adjustment to the cost and/or time with the contractor.

22
Q

When does the contractor’s warranty period start?

A

This begins when the project has reached substantial completion.

23
Q

What post-construction activity is a prerequisite for LEED certification?

A

Commissioning of the energy systems is a prerequisite for this.

24
Q

What activity must take place if the architect determines the project is not substantially complete after a site inspection?

A

The architect must notify the contractor of the work that must be completed to achieve this.

25
Q

Why would an architect provide a post-occupancy evaluation free of charge to the owner?

A

This activity provides valuable information to the architect after the owner has occupied the building. It is a good marketing effort by the architect and maintains contact with the owner for potential future work.

26
Q

What action may the owner take upon the acceptance of substantial completion by the parties?

A

When this is reached, the owner may move in or utilize the work for its intended purpose.

27
Q

For a large, complex building project, who usually hires the commissioning agent?

A

This person is hired by the owner to coordinate the efforts of this post-construction activity.

28
Q

What is the next activity after the contractor has completed the punch list?

A

After the contractor has completed this, the next step is for the architect to make an inspection to determine whether the project is substantially complete.

29
Q

If a construction claim is made by the contractor, what actions may be taken by the initial decision maker?

A

If the contractor takes this action, the initial decision maker may do any of the following:

+ Request supporting data.

+ Suggest a solution.

+ Accept the contractor’s assertion.

+ Reject the contractor’s assertion.

+ Notify the parties that a determination cannot be made.