.AR Conduct of OPS (40DP-9OP02) & ODPs: Welch's Highlighted Notes Flashcards
Conduct of Ops (40DP-9OP02 and ODP-1):
Unit Ops Managers:
- ?
Unit 1 Shift Manager specific duties:
- ?
Conduct of Ops (40DP-9OP02 and ODP-1):
Unit Ops Managers:
- Holds SRO license (senior license holder)
Unit 1 Shift Manager specific duties:
- Primary contact between the Units and WRF
- Responsible for, and has authority as a Senior Licensed Operator, to suspend safeguards or any other actions taken per 10CFR50.54(x) & (y) relating to the unit common areas of the facility.
-
ISFSI (conditional surveillance, inspections, and implementation of E-plan activities)
- Unit specific dry cask activities / transport owned by that unit’s SM.
Conduct of Ops (40DP-9OP02 and ODP-1):
STA:
- specific duties?…
Outage Communications:
- All communications between the MCR and Operations 4th floor supervision support or OCC is through…who?…
Conduct of Ops (40DP-9OP02 and ODP-1):
STA:
- Reviews completed OPS STs.
- Evaluates seismic events.
- Attends pre-test briefings, maintenance activity tail-board meetings, and pre-critical evolution briefings.
- Maintains presence in MCR during performance of planned complex or safety related tasks involving coordination of detailed time or sequence dependent actions.
- Risk assessments and protected equipment
- Operability determinations
- Immediately responds to STSC when notified of condition that may require REP classification or entry into EOP/AOPs.
- Recommends quarantine of equipment for troubleshooting.
- Advises the on-shift EC on appropriate classifications, notifications and PARs.
Outage Communications:
- All communications between the MCR and Operations 4th floor supervision support or OCC is through the SM
Shift Manning (4.8 / ODP-2)
- Minimum shift manning?… Exceptions?… Refuel SRO?…
- ENS Communicator(s)?…
- STSC Communicator(s)?…
Shift Manning (4.8 / ODP-2)
-
Any position (except the SM) can be unfilled for < 2 hours (emergency only)
- However, an SRO can be upgraded to SM by Ops Manager. If SM left, an on-site SRO (CRS) could become “SM” until relieved within 2 hours.
- One SM per unit
- One CRS per unit
- Two ROs per unit
- One FTA: One unit shall have an additional RO (may fill an AO position) Site Fire Team Advisor. (7 total)
-
Four AOs per unit
- One AO on site proficient RW operator
- One AO on site qualified to run the SBOGs
- One extra AO in Unit 1 for “Outside Area Watch”
- One STA per unit (3 total) OR two STAs on site and one ENS communicator.
-
Two ROs and three AOs shall be present within each unit at all times.
- Within the Unit: Area containing each unit bounded by PA fence and fences running north and south between the spray ponds and adjacent unit.
- The 4th AO must be in communication with the MCR and be able to return within 10 minutes.
- AOs can be reduced to 2 on a unit if support is needed on another unit during a Significant Event (SM permission)
- AO is part of the crew composition if they are on site and in direct communication with the MCR via radio or pager.
- Refuel SRO – Directly supervises all core alterations
-
One ENS Communicator per unit (3 total)
- Stationed when continuous NRC communications required (Alert or higher) or requested
- Has no other E-plan duties. Separate from the STSC Communicator.
- ENS communicator is knowledgeable of the plant (RO, SRO, STA, AO or a previously licensed).
- Usually covered by the STA from another unit (if 3 STAs are on-site)
- Two STSC Communicators for the site (2 total)
Shift Manning (4.8 / ODP-2):
MCR Staffing:
- Fuel in vessel?
- OATC?…
- Modes 1-4?…
- Modes 5-6?…
Night Orders: Explain…
Standing Orders:
- Explain…
Shift Manning (4.8 / ODP-2):
MCR Staffing:
- Fuel in vessel: one licensed operator in OATC area at all times
- OATC or CRS remains in MCR at all times
-
Modes 1-4:
- CRS remains in the “At The Controls Area” or “Briefing Area”
- Maintains command function unless relieved.
- Short duration access to STSC or SM office is permitted without relief.
- STA within 10 minutes of the MCR
- Modes 5-6: CRS normally has command function, may be a qualified SRO or RO.
Night Orders: Provide info to Ops personnel in a timely manner. Considered temporary in nature and are of a shorter term than Standing Orders.
Standing Orders:
- Disseminate information related to longer term issues that may require additional Operations actions
- Additional monitoring required from Operability Determination (OD) contingency plans or ODMI action plans
- Directives from Operations Manager.
Alarm Response / Requirements:
- Alarms are communicated directly to who?…
- Silencing alarms:
- Alarm Acknowledge: what do you do?…
- Flasher Reset: what do you do?…
- SM or CRS permission is required to do what?…
Alarm Response / Requirements:
- Alarms are communicated directly to the CRS and prompt action is taken to identify the cause. If known, report both RJ and RK.
- Treat as valid until proven otherwise.
- Silencing alarms:
- Alarm Acknowledge: scan all boards for other alarms.
- Flasher Reset: scan the affected board, at a minimum, for other alarms.
- Multiple, simultaneous alarms may be grouped under one announcement that is most appropriate to the observed condition
- MCR refers to local ARP when AOs are directed to perform local ARPs
- An ALARM (ALL) screen shall be displayed on B01, B04, or B06 during shift operation and shift turnover.
- SM or CRS permission is required to deselect the screen due to other monitoring needs for plant conditions.
Expected Alarms:
- Communicated to who ahead of time?…
- Are alarms not pre-briefed with the CRS are considered unexpected?…
- ?
Unexpected Alarm:
- Which alarms are unexpected?…
Expected Alarms:
- Communicated to CRS ahead of time.
- All alarms not pre-briefed with the CRS are considered unexpected.
- If an alarm comes in that was not pre-briefed, but is related to an activity and should have been pre-briefed: validate the alarm using available indications and the ARP to ensure no further action is required. ARP is performed at the discretion of the CRS.
- Expected alarm: verify on plant computer, communicate it to the CRS, and state the reason.
- Repeat alarm announcements can be suspended with CRS permission.
- ARP use is not required for expected alarms unless equipment manipulations are required
Unexpected Alarm:
- All alarms other than expected.
- Requires continuous use for the ARP (first response of the shift)
- ARP does not have to be referenced for subsequent alarms unless manipulations are required.
Alarm Abnormalities/Computer Alarms:
- ?
- RMS alarms…how fast reported once they come in?…
Fast Flash/Locked In:
- CRS authorizes any annunciator left in which flashing mode?…
- ?…
Alarm Abnormalities/Computer Alarms:
- Communicate alarm to the CRS.
- CRS determines the appropriate response.
- RK alarm with no computer point alarms (RJ).
- RJ alarm with no associated control board alarm window (RK) or RMS alarms.
- RMS alarms promptly reported (potential AOP/EOP entry, LCO entry, and/or E-Plan Classifications)
- Fully investigate / write CR.
Fast Flash/Locked In:
- CRS authorizes any annunciator left in fast flash.
- CRS determines the appropriate duration (≤ 1 hour), monitoring requirements, and required contingency actions.
- Alarms NOT to be left in fast flash condition (alarm is required to meet the LCO requirements, only if in the mode of applicability)
- CEA Position Out-Of-Limits (4A06B) - PDIL LCO
- Possible Inadvertent Boron Dilution (3A05B) – BDAS LCO
- CTMT Sumps Excess Leakage (7B03B) - RCS Leakage Detection LCO
Transient Alarm Management:
- ?…
Fire Protection Alarms within the Power Block:
- ?…
Transient Alarm Management:
- Operators should announce critical alarms
- CRS updates the crew when transient alarm response is entered.
- Automatically occurs following a reactor trip or cutback.
- CRS directs the transition back to the use of normal alarm response (once the plant is stable)
Fire Protection Alarms within the Power Block:
- SM/STA immediately notified of actual “Fire” alarms to evaluate E-plan.
- Operations only operates fire protection equipment during emergent situation or to protect equipment and/or area damage.
Manual SESS Inputs:
- ?…
Manual SESS Inputs:
- Initiated when any monitored component or system is Inoperable:
- Disabled and unable to perform the intended function by any method that is not alarmed
- Examples: filling SIT with B HPSI pump, local 3.6.3 admin controls
- Required if impairment or failure is anticipated to last longer than the current shift.
- Should be initiated at the time of the occurrence but in all cases shall be in place prior to shift turnover.
- Document initiation, removal, and reason for SESS manual inputs in the Unit Log.
- Initiate a Technical Specification Component Condition Record (TSCCR) if applicable.
- CRS informed of all SESS panel changes.
Automatic Actions (4.6.2):
- ?…
Equipment Hand Switch Positioning Following Actuation (ODP-1 14.0):
- ?…
Automatic Actions (4.6.2):
- Validate automatic initiations and actuations occur. Ensure actions take place in response to valid initiation signals, unless such action complicates a transient or is prohibited by procedure.
-
Failure of an automatic action:
- Informs the CRS prior to performance of an action
- Manually perform the actions necessary to fulfill the function
- Report completion of the manual action to the CRS
-
Approved actions without referencing a procedure:
- Tripping the main turbine if trip setpoint exceeded
- Starting a standby pump if it fails to auto start.
- Initiating a cutback due to automatic failure.
- Tripping a MFP on loss of NNN-D15 or NNN-D16
- Starting Standby Charging Pump
- Manually actuating a reactor trip or ESFAS if setpoint exceeded and it did not occur. (Does NOT require CRS concurrence)
Equipment Hand Switch Positioning Following Actuation (ODP-1 14.0):
- Does NOT apply to equipment with override capability (PZR HTRs) OR systems with independent control systems (IA Compressors).
- Match the HS for Non-class** equipment that **auto started or tripped on bus undervoltage.
-
Class equipment: Only match HS per a procedure OR as directed by CRS
- May actuate an override OR cause equipment damage.
Prompt and Prudent Mitigating Actions (4.7.5):
- CRS concurrence needed?
- ?…
Manual Override of Automatic Systems (4.7.14):
- CRS concurrence required prior to what?…
- ?…
Prompt and Prudent Mitigating Actions (4.7.5):
- CRS concurrence
- Mitigates complications due to equipment malfunctions or degrading plant conditions
- Action is allowed (from memory) to place plant in stable condition.
- Only if inaction would result in:
- unwarranted/preventable shutdown LCO entry
- imminent equipment damage
- plant transient (reactor trip, turbine trip, cutback, loss of letdown, reactivity excursion, etc.)
- personnel injury
- Confirm actions with the procedure as soon as possible.
Manual Override of Automatic Systems (4.7.14):
- CRS concurrence required prior to transfer (auto or manual)
- Discuss during PJB for normal procedures (expected duration / contingency actions)
-
If auto function fails and manual control must be taken, immediately notify all MCR of controller status
- As time permits, discuss manual control, potential transients, post trip requirements, etc.
- If the operator believes a transient can be controlled by taking manual control, then the operator should do so immediately and inform the other MCR personnel of the action.
- CRS shall state his acceptance or direct alternate actions_._
MCR expectations (4.6.2):
- Keys should not be left in key lock switches, except for?...
- Eating in MCR: ?…
MCR expectations (4.6.2):
- Keys should not be left in key lock switches, except for CPC keys and “captured” keys which must remain in place. Keys may be left in HSs as long a procedure is in-progress.
- Eating in MCR: MCR personnel only (includes non-ops personnel that have to stay in MCR). Limited to individual servings. At no time are food or beverages allowed while operating the controls.
Control Room Access:
- Free access limited to who…?…
- ?…
Control Room Access:
- Free access limited to on shift Control Room staff and the NRC.
- All non-operations personnel must have a business need and permission from the on shift CRS or SM to enter.
- Any MCR staff may grant other members of the on shift Operations crew or Work Control (WC) operators permission to enter, permission may be granted in person at entrance, or via phone/radio prior to entry.
- OATC permission to access the area forward of CRS desk.
Board Monitoring / Walkdown Requirements (4.6.4 – 4.6.6):
- CRS walkdown (B01 to B07) at what time during the shift?
- ?…
Board Monitoring / Walkdown Requirements (4.6.4 – 4.6.6):
- CRS walkdown (B01 to B07) at turnover and mid-shift.
- BOP and OATC board walkdown every 2 hours (alternate every hour)
- OATC monitors critical parameters every 5 minutes
- OATC responsible for:
- B02 to B06 (Modes 1-4)
- B02 to B04 (Modes 5, 6, defueled)
- Responds to other boards if BOP is not in the MCR
- BOP monitors boards not covered by the OATC
Critical Parameters checked every 5 mins:
1. During Power Operations:
• Reactor power
• RCS temperature and pressure
• Pressurizer and VCT level
• Steam generator level and pressure
• Steam/feedwater flow
• Main generator output
• Main condenser vacuum
• Other important parameters as directed by unit risk
2. During Shutdown Conditions with fuel in the vessel:
• RCS inventory, temperature and pressure
• Shutdown cooling flow and temperature
• Nuclear instrumentation
• Other important parameters as directed by the Shutdown Risk Assessment
Procedure Usage:
- CRS concurs with procedure which procedure sections?…
- Knowledge Based Conditional Steps (4.7.4.10):
- If decision will result in placing the plant in a non-normal or non-standby alignment during non-transient conditions, the authorizing SRO shall obtain a peer review by a second qualified?…
- If WCC authorizes knowledge based procedure conditional statements, then communication of the authorized activity to the CRS shall be performed when?…
-
Use of N/A:
- Is it possible to N/A steps ahead of time?…
- if not possible, then…?
- STs: do what to completed steps?…
- GOPs: do what to completed steps?…
Procedure Usage:
- CRS concurs with procedure sections to be used for each evolution (can be delegated to other supervisors).
- Knowledge Based Conditional Steps (4.7.4.10)
- If decision will result in placing the plant in a non-normal or non-standby alignment during non-transient conditions, the authorizing SRO shall obtain a peer review by a second qualified SRO or other qualified supervisor.
- If WCC authorizes knowledge based procedure conditional statements, then communication of the authorized activity to the CRS shall be performed prior to performing work for activities with Control Room impact
-
Use of N/A:
- If possible, N/A steps ahead of time (task has options for completion, conditions not met, etc.)
- If not possible to identify the contingency prior to task performance, steps may be marked N/A during task performance.
- STs: initial completed steps
- GOPs: initial and date completed steps