APM PFQ Sample Exam Flashcards
Question 1 Which of the following is not a stage in an issue resolution process? a. Share the issue with stakeholders. b. Track the issue to closure. c. Escalate to the sponsor. d. Apply change control.
a. Share the issue with stakeholders.
Question 2
Which of the following are challenges for a project manager developing and leading a project team?
1) Issues and incompatability amongst team members
2) Getting the right skills and attributes amongst team members
3) Co-location of team members in the same geographic area
4) Lack of accountability of team members
a. 1, 2 & 3
b. 1, 2 & 4
c. 1, 3 & 4
d. 2, 3 & 4
b. 1, 2 & 4
Question 3 Which of the following is an activity in a typical change control process? a. Recommendation. b. Justification. c. Planning. d. Continuous improvement.
a. Recommendation.
Question 4
The purpose of quality assurance is to:
a. provide confidence the project will satisfy the relevant quality standards.
b. determine a set of procedures and standards for project management.
c. inspect, measure and test deliverables and processes.
d. define the scope and specifics of a project’s deliverables.
a. provide confidence the project will satisfy the relevant quality standards.
Question 5
A project manager might use a PESTLE analysis in order to:
a. mitigate all possible risks to the project.
b. identify and mitigate factors that may affect the project.
c. control technological change during the project.
d. consider team social roles in early stages of the project.
b. identify and mitigate factors that may affect the project.
Question 6 Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development a. 3 and 4 only b. 1, 2 and 3 c. 1 and 2 only d. 2, 3 and 4
d. 2, 3 and 4
Question 7
Which of the following is the responsibility of a project manager?
a. Ensuring a project is aligned to the organisation’s strategy.
b. Focusing on project benefits and aligning priorities.
c. Achieving the project’s success criteria.
d. Improving process, tools and techniques used in a project.
c. Achieving the project’s success criteria.
Question 8 To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis? a. Budget. b. Stakeholder. c. Resource. d. Schedule.
b. Stakeholder.
Question 9
Which of the following is a responsibility of the project sponsor?
a. Creating a project cost breakdown structure.
b. Authoring the project management plan.
c. Creating a project work breakdown structure.
d. Owning the project business case.
d. Owning the project business case.
Question 10
Portfolio management includes prioritising:
a. projects and/or programmes that contribute directly to the organisation’s strategic objectives.
b. projects with exceptionally high returns on investment.
c. projects and programmes over business as usual.
d. projects which maximise change over those which maximise investment.
a. projects and/or programmes that contribute directly to the organisation’s strategic objectives.
Question 11
Which of the following actions would not help a team leader influence the performance of
their team?
a. Creating an exclusive environment.
b. Providing clear roles and responsibilities.
c. Promoting openness and honesty.
d. Developing a trusting relationship.
a. Creating an exclusive environment.
Question 12
One difference between a project and business as usual is:
a. projects achieve specified benefits but business as usual has only vague benefits.
b. projects drive change whereas business as usual continues existing activities.
c. projects have tightly controlled budgets whereas business as usual does not.
d. projects have unclear deadlines but business as usual has multiple milestones.
b. projects drive change whereas business as usual continues existing activities.
Question 13
The purpose of project progress reporting is to:
a. ensure a simpler critical path.
b. enable the tracking of project deliverables.
c. ensure stakeholder acceptance of project deliverables.
d. provide an increased total float.
b. enable the tracking of project deliverables.
Question 14
Which of the following is the purpose of an estimating funnel?
a. Keeping resource usage to a minimum to help reduce costs.
b. Supporting the production of comparative estimates.
c. Identifying where costs can be minimised when preparing a budget.
d. Representing increasing levels of estimating accuracy achieved through the life cycle.
d. Representing increasing levels of estimating accuracy achieved through the life cycle.
Question 15
One advantage of virtual communications is:
a. that nonverbal signals can have an impact on discussions.
b. it’s easy to detect signs of conflict within the project team.
c. access to a wider resource pool for the project.
d. that the project team will always be co-located.
c. access to a wider resource pool for the project.
Question 16 Which technique could be used by a project manager when resources are limited? a. Resource aggregation. b. Resource estimation. c. Resource levelling. d. Resource expansion.
c. Resource levelling.
Question 17
The main aim of quality management is to:
a. prepare a high-quality management plan.
b. ensure that deliverables meet appropriate standards.
c. validate the use of consistent standards.
d. determine whether to accept change requests.
b. ensure that deliverables meet appropriate standards.
Question 18
Which of the following is a purpose of issue management?
a. To stop issues occurring within the project.
b. To address and resolve the issues that occur.
c. To address and resolve uncertainty.
d. To reschedule activities to reduce costs.
b. To address and resolve the issues that occur.
Question 19 Product breakdown structures illustrate the required scope of work by a hierarchical structure itemising the: a. components of each product. b. budget of each product. c. benefits of each product. d. risks of each product.
a. components of each product.
Question 20
The definition of benefits management includes which key activities?
a. Planning, analysis and integration of project benefits.
b. Justification, validation and acceptance of project benefits.
c. Identification, tracking and realisation of project benefits.
d. Realisation, acceptance and integration of project benefits.
c. Identification, tracking and realisation of project benefits.
Question 21
Which of the following statements about scheduling is false?
a. Defines the sequence of activities.
b. Considers work calendars and time contingency.
c. Provides a baseline for safety considerations.
d. Quantifies the required resources.
c. Provides a baseline for safety considerations.
Question 22
Which of the following defines the term ‘deployment baseline’?
a. The starting point for creating a resource histogram.
b. The basis for creating an organisational breakdown structure.
c. The starting point for the monitoring of project risks.
d. The basis for progress monitoring.
d. The basis for progress monitoring.
Question 23 Which of the following is an activity in a typical configuration management process? a. Evaluation. b. Identification. c. Registration. d. Justification.
b. Identification.
Question 24
Stakeholder analysis supports effective stakeholder engagement by:
a. identifying stakeholders with high levels of power and interest.
b. ensuring stakeholder acceptance of project deliverables.
c. justifying the preferred project option to stakeholders.
d. providing information to all stakeholders.
a. identifying stakeholders with high levels of power and interest.