API 575 Section 7 Flashcards
Which of the following should be immediately addressed by either the inspector or tank engineer?
A. Isolated pitting up to 0.050” deep on the plate-extension
B. Hole in a tank roof
C. Insulation on north side of tank with algae growing
D. Tight temperature crack in the concrete ring-wall
B. Hole in a tank roof (7.1.2.1)
Which of the following should be checked after very high winds or heavy rain? This may have more than one correct answer, select all answers that apply.
A. External floating roof seals B. Foundation deterioration
C. Soundness of the floating roof legs
D. Water loads on external floating roof tanks
A. External floating roof seals, B. Foundation deterioration, D. Water loads on external floating roof tanks (7.1.2.2)
Inspection intervals that are based on past and current performance are called:
A. Condition-Based intervals.
B. Fitness-for-Service intervals. C. RBI intervals.
D. Time-Based intervals
A. Condition-Based intervals. (7.2.1)
Determine the corrosion rate occurring on a shell course based on this data.
tmin 10/2021 4/2017
0.525” 0.570” 0.588”
A. 3.6 mpy (mils per year)
B. 4.0 mpy
C. 4.5 mpy
D. 10 mpy
B. 4.0 mpy (7.2.2 – see calc pg 54)
Time Period=2021 10/12–2017 4/12 = 2021.83 – 2017.33 = 4.5 yrs
Corr Rate = Metal Lost / Time = (588 – 570) / 4.5 = 18 / 4.5 = 4 mpy (or 0.004 ipy)
Determine the Remaining Life for a shell course based on the following data.
tmin 6/2008 6/2017 11/2021 0.344” 0.422” 0.395” 0.368”
A. 3 years
B. 4 years
C. 6 years
D. 9 years
B. 4 years (7.2.2 – see calc pg 54)
Calculate Long Term Corrosion Rate:
Time Period = 2021 11/12 – 2008 6/12 = 2021.92 – 2008.5 = 13.42 yrs
Corr Rate = Metal Lost / Time = (422 – 368) / 13.42 = 54 / 13.42 = 4 mpy (or 0.004 ipy)
Calculate Short Term Corrosion Rate:
Time Period = 2021-11/12 – 2017-6/12 = 2021.92 – 2017.5 = 4.42 yrs Corr Rate = Metal Lost / Time = (395 – 368) / 4.42 = 27 / 4.42 = 6.1 mpy (or 0.0061 ipy)
Select Controlling Corrosion Rate:
Larger of Long or Short = 6.1 mpy
Calculate Remaining Life: Life = Remain Corr Allowance / Rate = (368 – 344) / 6.1 = 3.94 yrs
Round up to 4 yrs
In the tank construction code, API 650, the needed shell thickness are calculated. Which of the follow statements is correct?
A. Calculations are based on a 4-to-1 safety factor.
B. One calculation applies to all courses. (one tmin for the entire shell)
C. In most cases, the tmin calculate actually has some excess thickness.
D. The formula always used is called the Variable-Design-Point method.
C. In most cases, the tmin calculate actually has some excess thickness. (7.3.1.2)
For new tanks built to API 650, the new thickness for the shell plates:
A. should never be less than ½”.
B. considers only the shell stresses resulting from the product.
C. considers only the shell stresses resulting from the hydrotest water.
D. considers both shell stresses resulting from the product & the hydro water.
D. considers both shell stresses resulting from the product & the hydro water. (7.3.1.3)
While in operation, which tank component has a low membrane stress?
A. Bottom plates away from the critical zone and any annular plates
B. Annular plate
C. Bulged area on the shell
D. Nozzle-to-shell weld on a tank product nozzle
E. Shell vertical welds
A. Bottom plates away from the critical zone and any annular plates (7.3.1.3)
The Variable-Design-Point method is always used to calculate the tmin of:
A. annular plates.
B. nozzles.
C. tank shells over 200’ in diameter.
D. all tank shells.
C. tank shells over 200’ in diameter. (7.3.1.3)
If a tank is subject to external pressure (a vacuum), the shell tmin should be calculated using:
A. API 650’s 1-foot method.
B. API 650’s Variable-Design-Point method.
C. API 653’s Annex H.
D. API 650’s Annex V.
D. API 650’s Annex V. (7.3.1.3)
A large area on a shell course is corroded below acceptable limits. Which of the following is not an acceptable option?
A. Change to a product with a lower specific gravity
B. Coat the corroded area with a lining
C. Lower the fill height
D. Replace the corroded area
B. Coat the corroded area with a lining (7.3.1.4)
An isolated deep pit in the shell:
A. does not appreciably weaken the shell.
B. must always be repaired.
C. never needs to be repaired. D. should be evaluated per API 580.
A. does not appreciably weaken the shell. (7.3.2.1)
Neither API 650 or API 653 have a method for determining the minimum required thickness of a tank’s:
A. annular plates.
B. floor plates.
C. nozzles.
D. shell plates.
C. nozzles. (7.3.2.2)
Roof supports are normally:
A. designed per AISC’s Steel Construction Manual.
B. designed per API 650.
C. made from 3/16” steel.
D. made from pipe.
A. designed per AISC’s Steel Construction Manual. (7.3.2.3)
The Internal Inspection interval in API 653 is normally controlled by the corrosion on the:
A. bottom.
B. nozzles.
C. shell.
D. thinnest component.
A. bottom. (7.4.1)