APC Conflict avoidance, management Flashcards

1
Q

What is ADR?

A

Alternative Dispute Resolution (ADR) provides a confidential and alternative method of tackling legal disputes which avoids going to court. The most common types of ADR are conciliation and mediation, arbitration and adjudication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do you understand by the term conflict?

A

A conflict of interest is a situation in which an individual has competing interests or loyalties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can conflict be good?

A

Yes -

Can provide solutions to problems

Challenging old processes

Creates new opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How can conflict be bad?

A

Drives bad behaviour

Isolated working

Detrimental to the project’s objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Is there a healthy level of conflict?

A

Yes which can be good and conflict avoidance can be incorporated. If there is too much conflict then Dispute resolution maybe needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can we avoid conflict pre contract?

A

Appropriate Contract Selection

Appropriate Risk Allocation

Quality Check to Contract Information and

Works Information

Tender Scoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How can we avoid conflict post contract?

A

Proper administration of the Contract

Highlight issues early

Keep up to date, logically correct programmes – push for Accepted Programme

Proactive Risk Reduction Meetings

Keep Minutes and Actions

Reduce Confrontational Language

Working Groups to Resolve Outstanding
Issues Before Snowballing

Hands Up When You’re Wrong.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is mediation?

A

Mediation is a way of settling disputes in which a third party, known as a mediator, helps both sides to come to an agreement that each considers acceptable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is adjudication?

A

Adjudication is a compulsory dispute resolution mechanism that applies to the UK’s construction industry.

Statutory adjudication was introduced by the Housing Grants, Construction and Regeneration Act 1996 (Construction Act 1996).

Is a 28-day procedure (although the parties can agree to extend this period).

described as a “pay first, argue later” mechanism for resolving disputes

Interim binding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is arbitration?

A

Arbitration is a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case.

The arbitrator may be a lawyer, or may be an expert in the field of the dispute.

Legally Binding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is litigation?

A

Litigation is the process of engaging in or contesting legal action in court as a means of resolving a dispute. The court is able to enforce or determine one party’s rights or obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is expert determination?

A

Expert determination is a process in which an independent third party who is an expert in the subject matter is appointed to decide the dispute. The expert’s decision is binding on the parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How in conflict avoidance managed within TfL?

A

TfL and its contractors have worked with RICS to develop the Conflict Avoidance Panel. CAP is a panel of between one and three people that can be appointed at short notice when issues arise and produce a non-binding recommendation within 21 days of the appointment.

This is non binding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do we do it under the Contract?

A

Either Party has the right to bring litigate action

As long as the Parties are bound by a Construction Contract, either Party has the right to Adjudicate at any time.

Options W1 (all other contracts outside of W2) and W2 (for UK where it is a Construction Contract) of NEC3 and W3 of NEC4 are the Dispute Resolution options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do we do it under the Contract?

A

Either Party has the right to bring litigate action

As long as the Parties are bound by a Construction Contract, either Party has the right to Adjudicate at any time.

Options W1 (all other contracts outside of W2) and W2 (for UK where it is a Construction Contract) of NEC3 and W3 of NEC4 are the Dispute Resolution options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the adjudication process?

A
  • Notification of Adjudication from one party to another.
  • From receipt of notification, parties have up to 7 days to appoint the adjudicator.
  • Adjudicator will review parties cases, and make their decision within 28 days. (This can be extended to 42 days)
  • The adjudicator does not have the power to award costs, unless the parties agree to grant him this power.