AOP-1 Flashcards
• Following a refueling outage, low power physics testing is being performed.
• Regulating Rod 37 is being withdrawn when it drops to the bottom of the core. Which of the following actions should be performed?
A. Commence emergency boration.
B. Retrieve the rod per SOP-6, Reactor Control System.
C. Insert all Regulating Rods to the Lower Electrical Limit.
D. Trip the reactor and go to EOP-1.0.
D. Trip the reactor and go to EOP-1.0.
If the Turbine Bldg. were to experience a loss of Non-Critical Service water due to a
piping system malfunction, which annunciators would alert the control room operators (
that a reactor trip was required?
A. EK-0260 H2 Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press.
B. EK-0259 Exciter Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press.
C. EK-0156/62 Condensate Pump Hi Temp, and EK-0259 Exciter Cooler Hi Temp.
D. EK-0259 Exciter Cooler Hi Temp, and EK-0260 H2 Cooler Hi Temp
B. EK-0259 Exciter Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press.
- Plant is at 80% power and was performing a power escalation to full power when EK-1364, “GASEOUS MONITORING HI RADIATION” annunciated.
- It is determined that this alarm is due to RIA-0631, Condenser Off-Gas Monitor in an alarm condition.
- PCS total gas activity is 0.17 j.JCi/cc.
- Off Gas flow is 3 cfm.
- At 0610 RIA-0631 indicated 8.00 E3 cpm.
- At 0635 RIA-0631 indicates 1.00 E4 cpm.
- “B” Steam Generator is the affected generator.
What actions should be taken to address the above plant conditions?
A. Trip the reactor and carry out the Immediate Actions of EOP-1.0, “Standard Post-Trip Actions”
B. Plant management must evaluate the need to perform a controlled Plant shutdown per GOP-8, “Power Reduction and Plant Shutdown”
C. Place the Plant in Mode 3 within 6 hours per ONP-23.2, “Steam Generator Tube Leak”, Step 4.2
D. Place the Plant in Mode 3 within 2 hours per ONP-23.2, “Steam Generator Tube
Leak”, Step 4.2
D. Place the Plant in Mode 3 within 2 hours per ONP-23.2, “Steam Generator Tube
Leak”, Step 4.2
A Critical Approach is in progress in accordance with GOP -3. Control Rods have
been withdrawn to 60 inches on Group 4, with dilution to criticality in progress. All (
required equipment is OPERABLE.
The following alarms are received in the Control Room:
- EK-0905, “SHUTDOWN ROD POSITION ABNORMAL”
- EK-0911, “ROD POSITION 41NCHES DEVIATION”
- EK-0912, “ROD POSITION8 INCHES DEVIATION”
- EK-0948, “DROPPED ROD”
The NCOR determines that Group B Shutdown Rod #19 has dropped into the core and is at 0 inches withdrawn as indicated on the PPC. The CRS implements ONP-5.1.
Which ONE of the following describes the subsequent actions that should be taken based on plant conditions?
A.Trip the reactor, implement EOP 1.0 and secure the dilution per ONP 5.1
B. Shutdown the plant and be in Mode 3 within 6 hours
C. Select Rod #19 and withdraw it to greater than 124” in accordance with SOP-6.
D. Lower all Shutdown, Part Length and Regulating Rods to their Lower Electrical Limits within 2 hours
A.Trip the reactor, implement EOP 1.0 and secure the dilution per ONP 5.1
During power operations, the following equipment is operating:
(
.. P-52C, Component Cooling Water (CCW) pump.
.. C-54, Waste Gas Compressor.
A Component Cooling Water leak occurs on the valve body of MV-CC117, SFP HXS
E-53A/B CCW INLET, on the 10” header to the Spent Fuel Pool Heat Exchangers. The following valid alarms are annunciating:
” EK-1172, COMPONENT CLG SURGE TANK T-3, HI-LO LEVEL “ EK-1368, RADWASTE PANEL C40 OFF NORMAL
“ EK-1167, COMPONENT CLG PUMPS P-52A, P-528, P-52C TRIP
CCW Surge Tank level continues to lower.
Which action(s) will enable restoration of the Component Cooling Water system?
A. Align T-2, Condensate Storage Tank, to supply T-81, Primary System Makeup Tank, loads to supply more makeup water to the CCW surge tank.
B. Close CV-0944, CCW TO RW Evaps and C-54, and close MV-CC184, SFP HX’s, RW EVAPs, & C-54 CCW Return.
C. Close CV-0944, CCW TO RW Evaps and C-54, and close CV-09778, CCW RETURN FROM RW EVAPS & C-54.
D Close CV-0944A, CCW to Spent Fuel Pool & Radwaste Evaps, and close MV-CC184, SFP HX’s, RW EVAPs, & C-54 CCW Return.
D Close CV-0944A, CCW to Spent Fuel Pool & Radwaste Evaps, and close MV-CC184, SFP HX’s, RW EVAPs, & C-54 CCW Return.
Plant is at 100% power and the alarm “Instrument Air Low Pressure” has just annunciated. Instrument air pressure stabilizes at 42 psig following actions taken to start available air compressors and crosstie of Feedwater Purity Air. Consideration to tripping the reactor should be given if:
A. deluge or sprinkler systems actuate.
B. CV-2083 closes and PCP Control bleed off to the VCT is lost.
C. CCW Hx Service Water Outlets CVs (CV-0823 and CV-0826} fail open. D CV-1359 (Non critical SW Header Isolation) closes.
D CV-1359 (Non critical SW Header Isolation) closes.
D CV-1359 (Non critical SW Header Isolation) closes.
Which ONE of the following conditions requires a reactor trip in accordance with Off-Normal Procedures?
A. Unidentified PCS leak at 0.9 gpm.
B. Steam leak which results in reactor power rising by 0.6% ( i
C. Primary to Secondary leak at 0.2 gpm and not rising.
D. Steam leak which requires a power reduction at 50% per hour
D. Steam leak which requires a power reduction at 50% per hour
Given the following plant conditions:
- Plant was originally in MODE 1 at 100% power
- A rapid power reduction was commenced at 300%/hr due to a loss of Cooling Tower Pump P-39A.
- No other equipment is out of service
Which ONE of the following requires a reactor trip per ONP-26, “Rapid Power Reduction?”
A. Tave at 520°F
B. PZR level at 62%
C. ‘A’ S/G level at 40%
D. ‘B’ S/G level at 90%
A’l Tave at 520°
Which ONE of the following conditions requires a reactor trip in accordance with Off-Normal Procedures?
A. A PCS leak at 1 gpm.
B. A Main Steam leak equivalent to 0.5% reactor power.
C. A stable Primary to Secondary leak of 0.5 gpm.
D. A Main Steam leak requiring a power reduction at 20% per hour.
C. A stable Primary to Secondary leak of 0.5 gpm.
With the Plant at 75% power as indicated on the highest of Delta T or Nl power, a feedwater transient occurs.
Which ONE of the following conditions would be used to determine if the reactor should be tripped?
A. Steam Generator levels 30% and lowering.,
B. Steam Generator levels 40% and lowering.
C. ‘‘A” main feed pump tripped annunciator alarming and “A” Throttle & Trip valves closed.
D. TAVE rising slowly.
A. Steam Generator levels 30% and lowering.,
Plant power is 85% as indicated on the higher of Delta T or Nl power, when a feedwater transient occurs.
Which ONE of the following conditions would be used to determine if the reactor should be tripped?
A. Steam Generator level(s) of 35% and stable.
B. Steam Generator level(s) of 45% and lowering.
C. “A” main feed pump trip annunciator alarming and Throttle & Trip valve closed.
D. TAVE rising slowly
C. “A” main feed pump trip annunciator alarming and Throttle & Trip valve closed.
The plant is operating at 65% power when both pressurizer spray valves fail OPEN.
Which ONE of the following actions must be performed? (
A. Raise PZR level to maintain pressure.
B. Secure PCPs as necessary to regain control of PZR pressure with PZR heaters.
C Trip the reactor and go to EOP-1.0.
D. Take manual control of selected Backpressure Regulating valve. ONP-18, Section 4.2.1
C Trip the reactor and go to EOP-1.0.
Given the following conditions:
Self-Study
- The plant is operating in MODE 1 at 45% power.
- A pressurizer spray valve has failed OPEN and PCS pressure CANNOT be maintained with pressurizer heaters.
Based on the above conditions which ONE of the following would be the appropriate action to take?
A. Close the spray valve.
B. Take manual control of the heaters.
C. Operate at a reduced pressure.
D Trip the reactor.
D Trip the reactor.
Conditions:
- The plant is at 100% power
- P-55A charging pump is tagged out-of-service
It is determined that PCS leak rate is 11.2 gpm unidentified. Your FIRST action would be to:
A. Attempt to locate the leak.
B Trip the reactor and enter EOP-1.0.
C. Ensure additional charging pumps start (if necessary).
D. Isolate letdown.
B Trip the reactor and enter EOP-1.0.
The plant is operating at 90% power when two (2) control rods drop. Which ONE of the following actions would be required?
A. Dilute PCS to maintain power stable.
B. Trip the reactor and go to EOP-1.0.
C. Borate PCS to lower power to
B. Trip the reactor and go to EOP-1.0.
- The plant is operating at 85% power.
- Cooling Tower Pump ‘B’ trips.
- Main Condenser vacuum begins lowering, as prescribed by ONP-14, “Loss of Condenser Vacuum”.
- The crew begins lowering power using ONP-26, Rapid Power Reduction.
- When power level reaches 55% during the power reduction, EK-0111, VACUUM LO, alarms due to vacuum at;c?4” Hg.
- Vacuum is at 22” and CONTINUES LOWERING. Which of the following actions are required to be taken?
A. Trip the turbine, verify the reactor automatically trips, and go to EOP-1.0, Standard Post-Trip Actions
B Trip the reactor, verify the turbine automatically trips, and go to EOP-1.0, Standard Post-Trip Actions
C. Continue the rapid power reduction until condenser vacuum stabilizes
D. Continue the power reduction, using normal de-escalation rates, until condenser vacuum stabilizes
B Trip the reactor, verify the turbine automatically trips, and go to EOP-1.0, Standard Post-Trip Actions
With the plant at 100% power, which one of the following conditions would require a reactor trip and entry into EOP-1.0, “Standard Post Trip Actions?”
A. Main Generator Exciter Cold Air Temperature is 76°C.
B. Critical Service Water Pressure is 51 psig.
C. Main Condenser Vacuum is 24.5” Hg.
D. Main Turbine vibration reading is 15.5 mils
D Main Turbine vibration reading is 15.5 mils
If the Turbine Bldg. were to experience a loss of Non-Critical Service water due to a piping system malfunction, which annunciators would alert the control room operators that a reactor trip was required?
A. EK-0260 H2 Cooler Hi Temp, and EK-1165 Non-Critical Serv Water La Press
B. EK-0259 Exciter Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press
C. EK-0171 Condensate Pump Room Flooding, and EK-0259 Exciter Cooler Hi Temp
D. EK.:0259 Exciter Cooler Hi Temp, and EK:•0260 H2 CoolerHi Temp
B. EK-0259 Exciter Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press
Given the following plant conditions:
- Plant is in MODE 1 at 100% power
- No equipment is out of service
Which of the following requires a reactor trip per ONP-12, “Acts of Nature?”
A. Lake water approaches the 590’ elevation
B. Lake water entering the Screenhouse
C. Tornado striking the facility
D. Earthquake felt on-site
B. Lake water entering the Screenhouse
Technical Specification 3.3.7 Post Accident Monitoring (PAM) Instrumentation is
required so that operators, following a major accident, will be able to monitor critical plant parameters. Which of the lists below contains only Post Accident Monitoring Instrumentation?
A. Wide Range Neutron Flux, Aux. Feedwater Flow Indication, and Reactor Vessel Water Level
B. Wide Range Neutron Flux, PCS Wide Range Pressure, S/G Wide Range Level
C. PCS Wide Range Pressure, Charging Header Flow Indication, Containment Area Radiation Monitors (high range)
D. S/G Narrow Range Level, PCS Wide Range Pressure, Core Exit Temperature Indications
B. Wide Range Neutron Flux, PCS Wide Range Pressure, S/G Wide Range Level
Given the following plant conditions:
Plant is in MODE 1 at 100% power No equipment is out of service
Which of the following is the lowest confirmed steam generator stable leak rate that requires a reactor trip per ONP-23.2, “Steam Generator Tube Leak?”
A. 0.15 gpm
B. 0.25 gpm
C. 0.35 gpm
D. 0.45 gpm
D. 0.45 gpm
Given the following plant conditions:
• Plant is in MODE 1 at 100% power
• No equipment is out of service
Which of the following requires a reactor trip per ONP-12, “Acts of Nature?”
A. Lake water approaches the 590’ elevation
B. Lake water entering the Turbine Building
C. Tornado striking the switchyard
D. Sustained heavy rains and high winds(> 4 hours)
B. Lake water entering the Turbine Building
Given the following plant conditions:
• Plant is in MODE 1 at 100% power
• No equipment is out of service
• A loss of load event occurs due to a complete failure of all EHC pumps When is a reactor trip required per ONP-1, “Loss of Load?”
A. Immediately
B. If Turbine controls cannot be placed in Manual
C. If Pressurizer pressure exceeds 2100 psia
D. If Tave cannot be restored within 3°F of TREF using control rods
A. Immediately
Given the following plant conditions:
Plant is in MODE 1 at 100% power No equipment is out of service
Which of the following requires a reactor trip per ONP-14, “Loss of Condenser Vacuum?”
A. Loss of Cooling Tower Pump P-39A
B. Main Condenser vacuum lowers to 20.8”Hg/
C. Main Condenser vacuum stabilizes at 24.5” Hg
D. Main Condenser vacuum lowers from 28” Hg to 25” Hg
B. Main Condenser vacuum lowers to 20.8”Hg/
Given the following plant conditions:
- Plant is in MODE 1 at 100% power
- No equipment is out of service
Which of the following requires a reactor trip per ONP-14, “Loss of Condenser Vacuum?”
A. Loss of Cooling Tower Pumps P-39A and P-398 -
B. Main Condenser vacuum lowers to 21.8” Hg
C. Main Condenser vacuum stabilizes at 24.5” Hg
D. Main Condenser vacuum lowers from 28” Hg to 25” Hg
A. Loss of Cooling Tower Pumps P-39A and P-398 -
Given the following plant conditions:
Plant was originally in MODE 1 at 100% power
A rapid power reduction was commenced at 300%/hr due to a loss of Cooling Tower Pump P-39A.
No other equipment is out of service
Which of the following requires a reactor trip per ONP-26, “Rapid Power Reduction?”
A. Tave at 530°F
B. PZR level at 63%
C. ‘A’ S/G level at 40%
D. ‘B’ S/G level at 90%
B. PZR level at 63%
Given the following plant conditions:
Plant was originally in MODE 1 at 100% power
A rapid power reduction was commenced at 300%/hr due to a loss of Cooling Tower Pump P-39A.
No other equipment is out of service
Which of the following requires a reactor trip per ONP-26, “Rapid Power Reduction?”
A. Tave at 530°F
B. PZR level at 60%
C. ‘A’ S/G level at 40%
D. ‘B’ S/G level at 96%
D. ‘B’ S/G level at 96%