AIC - Scheduling Flashcards
A Gant chart is which type of scheduling
tool?
bar chart
Which type of relationship is being shown in
Figure 7-3 between activities C and E?
finish to start
What type of relationship would best
describe “installing the scratch coat of
stucco” and then “installing the top coat of
stucco”?
finish to start
Using Figure 7-13, what is the early start for
activity G?
6
Using Figure 7-13, what is the late start for
activity H?
5
Using Figure 7-13, how much total float does
activity F have?
2
Using Figure 7-13, which activity is critical?
C
Using Figure 7-13, how much free float does
activity E have?
0
What classification of activity would “shop
drawing rejection” be?
procurement
What classification of activity would
“building programming” be?
design
Which of the following defines the term trade
stacking?
the loss of productivity by placing too
many workers in too small a space