AIC - Scheduling Flashcards

1
Q

A Gant chart is which type of scheduling

tool?

A

bar chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which type of relationship is being shown in

Figure 7-3 between activities C and E?

A

finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of relationship would best
describe “installing the scratch coat of
stucco” and then “installing the top coat of
stucco”?

A

finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Using Figure 7-13, what is the early start for

activity G?

A

6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Using Figure 7-13, what is the late start for

activity H?

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Using Figure 7-13, how much total float does

activity F have?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Using Figure 7-13, which activity is critical?

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Using Figure 7-13, how much free float does

activity E have?

A

0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What classification of activity would “shop

drawing rejection” be?

A

procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What classification of activity would

“building programming” be?

A

design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following defines the term trade

stacking?

A

the loss of productivity by placing too

many workers in too small a space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly