Agile Techniques: Scrum Flashcards
Stage 1: Product backlog
A prioritised list of original features that the system should contain, written as user stories/user cases
How are features prioritised?
Must have..
Should have..
Could have..
Won’t have..
What 3 things do user stories contain?
Identifier, Priority, Cost
Sprint backlog
The list of features are implemented and tested
Sprint process
Sprint planning -> Sprint review -> Sprint retrospective
Sprint planning
Select the product backlog items for this sprint
Sprint review
Meeting with client
Sprint retrospective
Team meeting after review
Daily stand-up
Team meets every day for 15 minutes
3 key roles in Scrum
A Product Owner, A Scrum Master, Development Team