run through of how to start a aee
document what is being proposed into its various parts
determine rules applicable from both rp and dp
if no rule in plans it will be permitted, except river bed e
arrange to meet council planners-important
duration sought
what is the final outcome of the see, i.e. what is it
a full explanation of all the effects of the activity and how it has avoided or mitigated them
so whats everything that needs to be in it
site details description of activity consultation effects how they are mitigated assessment against dp rp and section 3 of RMA and RPS
scaling method of effect (e.g. minor)
no effect
minor
major
critical
how to avoid remedy and mitigate a unsightly hole
avoid-locate somewhere it can’t be seen
remedy -fill in hole
mitigate-put plants in front
monitoring is not mitigation
the comprehensivness of the plan should be in proportion to
the effects
what is permitted baseline, and what is existing consents
permitted baseline is what is permitted without consents, like permitted activities, and
exisiting consents act as part of the environment already
consent processing steps (5)
receive application begin investigations notification or non notifcation draft conditions final decision