ABIC SW Definitions Flashcards

1
Q

Adjustment of time costs

A

Includes any loss, expense or damage reasonably incurred by the contractor that results from a delay due to the causes referred to in clause L1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Authorised person

A

A building inspector or certifier or other person authorised under relevant legislation having jurisdiction over the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Building code

A

Means volume one and two of NCC as in force as at the date of commencement of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Business day

A

Any day other than a Saturday, Sunday or Statutory public holiday in the state or territory shown in item 35 of schedule 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Claim to adjust the contract

A

A claim made to the architect to adjust the contract peace (including adjustment of time costs) or the date for practical completion or both

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract documents

A

Any special conditions shown in schedule 2, the conditions of this contract, the specifications, the drawings and any other documents shown in schedule 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract price

A

Clause N1
The contract price, shown in item 4 of schedule 1 is a lump sum and the contractor represents that the contract price allows for:
- everything reasonably required in accordance with this contract to complete the works
- all provisional and prime cost sums in Schedule 6 & 7
- installation of any items in schedule 8 to be supplied by the owner and installed by the contractor
- rise and fall
- all statutory taxes and charges applying 5 working days before tender closes
- import duties and tariffs on imported materials or equipment to be incorporated in or used in the completion of the works applying 5 working days before the tender closes
- exchange rates applying 5 working days before tender closes
- relevant industrial awards and work place agreements, site allowances, building industry superannuation levies and long service leave levies
- GST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost of building work

A

The actual net cost of the works excluding any amounts for GST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical construction activity

A

Clause L4.2
An activity which is part of the necessary work that if delayed will have a direct effect on subsequent activities such that the contractor’s ability to achieve practical completion by the date for practical completion will be affected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Defect or defective work

A

Work that is:
a. In breach of any of the warranties set out in the contract documents
b. Not in accordance with the standard or quality of building works specified in the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Detailed records

A

Clause J4.4
Written records maintained by the contractor of the hours worked and all other costs incurred by the contractor and the subcontractors in carrying out the variation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

GST

A

Goods and services tax levied under the GST Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

GST Act

A

A New Tax System (Goods and Services Tax) Act 1999

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Infrastructure service

A

A service to the site for which there is an alternative source of supplier or supply such as gas, electricity, telecommunications, water, stormwater or sewerage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Input tax credit

A

Has the same meaning as ‘input tax credit’ under the GST Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Insolvency event

A

In relation to a person, means anything that indicates that the person is or will become unable to pay their debts as and when they become due or payable including:
a. The person is declared, made or becomes insolvent
b. An execution or distress process is levied against the person’s assets which include the person’s income
c. The person enters into a deed of company arrangement with the person’s creditors
D. The person fails to comply with a bankruptcy notice or a statutory demand served under the corporation law
e. A provisional liquidator, liquidator, receiver, receiver and manager, administrator, scheme administrator, controller or other such administrator is appointed (whether by a court, creditor or otherwise) to the person or over the person’s assets
f. A trustee in bankruptcy, interim receiver, controlling trustee or other such administrator is appointed (whether by a court, creditor, or otherwise) to the person or over the person’s assets

17
Q

Latent condition

A

Clause F5.2
A physical condition on, underlying or adjacent to the site which a competent contractor would not have anticipated if the contractor had examined the site information and inspected the site before executing this contract

18
Q

Necessary work

A

All work including temporary work necessary to complete the works

19
Q

Non-working days

A

Statutory public holidays and rostered days off and recognized industry shut-down periods in the State of Territory shown in item 29 of schedule 1

20
Q

Official document

A

Clause B3.2
An official document is:
- any report, notice, order, permit, license, approval or other document required or issued by an authorised person in relation to the works
- Any document listed in item 30 of schedule 1
- any statutory approval
- an approval for provision of infrastructure services to the site
- any other document required under any relevant legislation

21
Q

Owner-specified materials

A

All items, materials, fixtures and fittings sources or supplied and requested by the owner to be incorporated into the works

22
Q

Party or parties

A

The owner or the contractor or both, as the case may be

23
Q

PPSR

A

The Personal Property Security Register, or equivalent national register for security interests in personal property from time to time

24
Q

Practical completion

A

Clause M1
The contractor must bring the works to practical completion by the date for practical completion shown in item 22 of schedule 1 as adjusted in accordance with the contract. The works are at practical completion when, in the reasonably opinion of the architect:
- they are substantially complete and any incomplete work or defects remaining in the works are of a minor nature and number, the completion or rectification of which is not practicable at that time and will not unreasonably affect occupation and use
- all commissioning tests for plant and equipment in item 28 of schedule 1 have been successfully carried out
- any approvals required for occupation have been obtained from the relevant authorities and copies of official documents evidencing the approvals have been provided to the architect

25
Prime cost sum
Clause K1.2 A prime cost sum shown in Schedule 7 is a sum exclusive of GST included in the contract for: - a foreseeable item of material or equipment, the precise identity of which was not known or had not been specified at the date of the contract - an allowance for payment of a fee or charge to a relevant authority
26
Promptly
As soon as practicable
27
Provisional sum
Clause K1.1 A provisional sum shown in schedule 6 is a sum exclusive of GST included in the contract for: - performance of foreseeable necessary work, including the supply of materials, not fully described by the contract documents on the date the contract was executed - connection of an infrastructure service to the site, if the detail of the infrastructure service required, or the supplier of the infrastructure service was not known or had not been finally decided on the date the contract was executed
28
Relevant authority
A body or organisation, statutory or otherwise, which has authority over the works in accordance with relevant legislation, including an infrastructure service supplier able to exclusively supply the site
29
Relevant legislation
Acts, regulations, official documents and official interpretations of them that have a direct relationship to the work being carried out by an authority having jurisdiction of the works
30
Site
The place at which the works are to be constructed and any other place made available by the owner to the contractor under the contract (described in item 6 of schedule 1)
31
Site information
Clause F3.2 Includes any reports, surveys, test results, plans, specifications, computations or other information such as foundation data, soils tests or geotechnical tests and any other information regarding the site and the physical conditions on and underlying the site shown in schedule 4
32
Tax invoice
An invoice for payment complying with the requirements of the GST Act
33
Unconditional guarantee
Clause C3.2 An unconditional undertaking or a performance undertaking from a recognised financial institution approved by the owner. The guarantee must be of an approved type. The type shown in schedule 5 is approved.
34
Valuable item
Clause F5.2 A valuable item includes minerals, money, treasure, fossils, archaeological remains, historic objects or relics
35
Variation
Clause J1.4 A variation is a change to: - the scope of the works as contemplated by the contract documents and capable of being executed under this contract - a dimension or level of the works - the materials, workmanship or quality of any part of the works - a detail of the works or - the order of precedence of the contract documents referred to in clause B2
36
Working day
Monday to Friday excluding non-working days
37
Works
The completed construction set out in the contract documents (described in item 5 of schedule 1)