8. Project Procurement Management Flashcards

1
Q

Owner

A

Define the scope of work
Provide evidence for having the financial capability
Provide evidence for the site title
Ect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Designer

A
Design the project 
Construction administration services 
Advising and consulting services 
Observing work progress
Ect.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Constructor (general contractor)

A

Review contract documents and field conditions
Construct the work safely according to the specs and drawings
Superintendence (supervise and direct the work)
Etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Multiple prime contractors

A

Advantages:
Save the cost of the GC profit and overhead
To finish the work early

Disadvantages:
Owner must perform the day to day management and coordination
Owner must perform general conditions responsibilities (site access, cleaning, office space, utilities)
Schedule challenges

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Design-Bid-Build (DBB) method

A

Most common government used method
Linear (sequential) process with no task overlap
Plans and specs are completed by the architect
After design is complete and accepted by the owner, bids are issued
Contractors bid the project exactly as it is designed and the lowest responsible responsive bidder is awarded the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Responsible bidder

A

Provide required payment bond and performance bond

Demonstrate the managerial and financial capabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Responsive bidder

A

Submit bid on time

Submit bid using required forms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction management (CM) methods

A

Construction manager as advisor

Construction management at risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CM as advisor

A

Consulting services

The owner interview and selects a fee-based firm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Construction manager (CM)

A

The CM provides pre construction services
Review the design
Ect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Construction management at risk

A
Guaranteed maximum price (GMP) 
The final construction price 
CM’m fees 
Overhead 
Contingencies 
All subcontractors selected by owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Design Build (DB)

A

The contractor and architect are only entity
Hired by the owner to deliver a complete project
GMP can be provided by DB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Engineering procurement construction (EPC)

A

The owner procures a single contract for design, equipment, construction

The EPC firm provides pre-construction services
Examples: oils refineries, mining plants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Integrated project delivery (IPD)

A

Multiparty contract

Shared risk/ reward delivery method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Consumption contracts (there are types)

A

Fixed price (lump sum)

Unit price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fixed price (lump some)

A

Scope is fully defined
Quantities are known
The owner knows the construction costs
The contractor accepts the bulk of the project risk

17
Q

Unit pride

A

Fixed unit price
Scope is fully defined
Quantities are unknown (the

18
Q

Cost reimbursable contracts

A

Known as cost plus fee
Scope is not fully defined
Uniqueness, schedule, and quality take precedent
Allows for construction to begin before design is completed
Owner typically assumes the risk of cost overrun
Contractor assumes the risk of schedule, quality, constructability, etc

19
Q

Guaranteed Max Price (GMP)

A

Can’t pay more than the max price

20
Q

Construction contract

A

An agreement between two parties that is enforceable by law

to control and allocate construction risk

21
Q

Mutual agreement

A

There must be a meeting of minds

22
Q

Purpose of construction contract is to deliver/produce

A

Safely
A quality construction project
On time
Within budget

23
Q

Typical contract provisions include

A
Scope for the work
Time of completion 
Contract sum 
Progress payment 
Retained percentage 
Schedule of value (SOS) - contract prices for specific items 
Work in place (% complete) and stored materials 
Acceptance and final payment
24
Q

Essential contract document

A
The agreement 
The general conditions 
The special conditions 
The drawings 
The technical specs
25
Q

The agreement

A
Date 
Names and addresses 
Description of the scope of work 
Time limitations 
Contract considerations 
Payment conditions 
References to other documents 
Signatures
26
Q

The general conditions (GCs)

A

Defines roles and responsibilities
Risk
Clauses used for contract administration

27
Q

The special/supplementary conditions

A
# of copies of contract documents 
Survey information 
Materials provided by the owner 
Cost and ached reporting requirements 
Deliverables start and finish dates  
Traffic controls requirements 
Testing requirements
28
Q

The drawings

A
Arch 
Struct 
Mech 
Elect 
Plumb
29
Q

The technical specs

A
Written requirements
Fully define requirements for materials, equipment, systems, standards, ect 
Quantity of materials 
Quantity of workmanship 
Election and instillation methods 
Etc
30
Q

Project manual

A

The complete written document or a set of documents that accompanied the plans

31
Q

Bonds (surety bong)

A

Written documents that describe the conditions and obligation related to the agreement

If the contractor is in breach of contract, the surety must complete the terms of the contract

32
Q

Bid bond

A

Assured the owner that the contractor will sign the contract or at least begin to perform on the contract

33
Q

Performance bond

A

Assured the owner that the contractor will compete the job

34
Q

Payment bond

A

Assured the owner that the contractor will pay labor, subcontractors, and suppliers