8. Project Procurement Management Flashcards

1
Q

Owner

A

Define the scope of work
Provide evidence for having the financial capability
Provide evidence for the site title
Ect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Designer

A
Design the project 
Construction administration services 
Advising and consulting services 
Observing work progress
Ect.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Constructor (general contractor)

A

Review contract documents and field conditions
Construct the work safely according to the specs and drawings
Superintendence (supervise and direct the work)
Etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Multiple prime contractors

A

Advantages:
Save the cost of the GC profit and overhead
To finish the work early

Disadvantages:
Owner must perform the day to day management and coordination
Owner must perform general conditions responsibilities (site access, cleaning, office space, utilities)
Schedule challenges

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Design-Bid-Build (DBB) method

A

Most common government used method
Linear (sequential) process with no task overlap
Plans and specs are completed by the architect
After design is complete and accepted by the owner, bids are issued
Contractors bid the project exactly as it is designed and the lowest responsible responsive bidder is awarded the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Responsible bidder

A

Provide required payment bond and performance bond

Demonstrate the managerial and financial capabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Responsive bidder

A

Submit bid on time

Submit bid using required forms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction management (CM) methods

A

Construction manager as advisor

Construction management at risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CM as advisor

A

Consulting services

The owner interview and selects a fee-based firm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Construction manager (CM)

A

The CM provides pre construction services
Review the design
Ect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Construction management at risk

A
Guaranteed maximum price (GMP) 
The final construction price 
CM’m fees 
Overhead 
Contingencies 
All subcontractors selected by owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Design Build (DB)

A

The contractor and architect are only entity
Hired by the owner to deliver a complete project
GMP can be provided by DB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Engineering procurement construction (EPC)

A

The owner procures a single contract for design, equipment, construction

The EPC firm provides pre-construction services
Examples: oils refineries, mining plants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Integrated project delivery (IPD)

A

Multiparty contract

Shared risk/ reward delivery method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Consumption contracts (there are types)

A

Fixed price (lump sum)

Unit price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fixed price (lump some)

A

Scope is fully defined
Quantities are known
The owner knows the construction costs
The contractor accepts the bulk of the project risk

17
Q

Unit pride

A

Fixed unit price
Scope is fully defined
Quantities are unknown (the

18
Q

Cost reimbursable contracts

A

Known as cost plus fee
Scope is not fully defined
Uniqueness, schedule, and quality take precedent
Allows for construction to begin before design is completed
Owner typically assumes the risk of cost overrun
Contractor assumes the risk of schedule, quality, constructability, etc

19
Q

Guaranteed Max Price (GMP)

A

Can’t pay more than the max price

20
Q

Construction contract

A

An agreement between two parties that is enforceable by law

to control and allocate construction risk

21
Q

Mutual agreement

A

There must be a meeting of minds

22
Q

Purpose of construction contract is to deliver/produce

A

Safely
A quality construction project
On time
Within budget

23
Q

Typical contract provisions include

A
Scope for the work
Time of completion 
Contract sum 
Progress payment 
Retained percentage 
Schedule of value (SOS) - contract prices for specific items 
Work in place (% complete) and stored materials 
Acceptance and final payment
24
Q

Essential contract document

A
The agreement 
The general conditions 
The special conditions 
The drawings 
The technical specs
25
The agreement
``` Date Names and addresses Description of the scope of work Time limitations Contract considerations Payment conditions References to other documents Signatures ```
26
The general conditions (GCs)
Defines roles and responsibilities Risk Clauses used for contract administration
27
The special/supplementary conditions
``` # of copies of contract documents Survey information Materials provided by the owner Cost and ached reporting requirements Deliverables start and finish dates Traffic controls requirements Testing requirements ```
28
The drawings
``` Arch Struct Mech Elect Plumb ```
29
The technical specs
``` Written requirements Fully define requirements for materials, equipment, systems, standards, ect Quantity of materials Quantity of workmanship Election and instillation methods Etc ```
30
Project manual
The complete written document or a set of documents that accompanied the plans
31
Bonds (surety bong)
Written documents that describe the conditions and obligation related to the agreement If the contractor is in breach of contract, the surety must complete the terms of the contract
32
Bid bond
Assured the owner that the contractor will sign the contract or at least begin to perform on the contract
33
Performance bond
Assured the owner that the contractor will compete the job
34
Payment bond
Assured the owner that the contractor will pay labor, subcontractors, and suppliers