8 - Critical path analysis Flashcards

1
Q

what is float?

A

latest finish time - duration - earliest start time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

lower bound for number of workers needed to complete a project within its critical time is smallest integer greater or equal to…

A

sum of all activity times / critical time of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly