5. Project Financial Control and Reporting Flashcards

1
Q

What is the purpose of project financial control?

A
  • Report and manage construction costs i.e. variations
  • Report to client Anticipated Final Account
  • Cash Flow Forecasting for monies required for interim payments.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What measures can be taken to effectively control costs during the construction phase of a project?

A
  • Regular cost reporting
  • Robust change control procedures
  • Management of provisional sums within budget
  • Rolling final account with closure process for financial impact of change
  • Management of provisional sums with budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Cost Report?

A

Financial report to client indicating changes in cost to a client during reporting period, reports to the client the Anticipated Final Account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Where can a QS find information of Cost Reporting?

A

RICS Guidance Note - Cost Reporting, 1st edition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What would you expect to find in a Cost Report?

A
  • Contract Sum
  • Provisional Sums
  • Contract Instructions
  • Anticipated Variations
  • Disputed Items
  • Loss & Expense
  • Cash Flow Forecast
  • Advance Warnings
  • Risk Allowance – Contingency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the frequency of a Cost Report?

A

Subject to client requirements and nature of a project i.e. scope of works, size of project etc.

Typically on my projects – cost reports are produced on a monthly basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How would you present a Cost Report to a client?

A

Typically within BTP Cost Reports, behind executive summary we include a ‘Summary of Changes’. Presenting a Cost Report to a client would include;

  • Discussing Executive Summary period of change
  • Talk client through Summary of Changes – answer any questions raised.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is outturn cost controlled by cost reporting?

A

Recognition of cost changes already incurred, planning for the implementation for future anticipated costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is good cost reporting?

A
  • Always accurately track cost and changes
  • Communicate changes effectively as and when required
  • Keep a rolling final account
  • Good cost report document to keep client informed
  • Good relationship with contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What costs would you exclude from a Cost Report?

A

A construction cost report would typically exclude professional fees, 3rd party costs, land costs, agency costs, finance cost, legal fees and VAT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Would you include Loss and Expense claims in Cost Report?

A

This would be included under a separate sub section in the report – Loss and Expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Would you include Liquidated Damages in a Cost Report?

A

Yes this should be included within liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Rolling Final Account?

A
  • All instructions and cost effects agreed up to the point of the latest financial report.
  • Final account statement would stand if works were to complete with no further changes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Drawdown Schedule?

A

Reports invoices due across reporting period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is included within a Drawdown Schedule?

A

Summary of invoices due for payments as of reporting period.

Breakdown reflecting – Professional Role & Fee, Anticipated Final Cost, Amount Due within each Drawdown, Total Approved and Outstanding Amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why are Drawdown Schedules important?

A
  • Recommendation of invoices due for payment.
  • Approval process for invoices raised – reviewed by BTP.
  • Reflects outstanding amount against invoiced – sufficient monies against programme
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a Cash Flow Forecast?

A

Projection of when payments are due to ensure finances are in place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Why is Cash Flow Forecasting important?

A

Ensure clients have required monies in place to make interim payments.

Can be used to monitor progress against forecasted cash flow.

Reflect actual cost against budgeted costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Different Types of Cash Flow?

A
  • Cash Flow Forecast for company.

* Cash Flow Forecast for specific project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the different methods for producing a Cash-Flow Forecast?

A
  • S-Curve = Standard Curve
  • Contractor’s Cash Flow
  • Computer modelling
  • Other special curve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is an S-Curve?

A

Standard Curve

Represents low expenditure at beginning of a project to reflect site set up and typically inexpensive enabling works & lower level of expenditure at the end of a project because of majority of materials on site and reduction of contractor’s overheads.

22
Q

What is a Contractor’s Cash Flow?

A

Once project tendered or contract entered into – more accurate than S-Curve.
The contractor can accurately assess cash flow requirements against programme and procurement schedule.

23
Q

What is Computer Modelling Cash Flow?

A

Computer predicted models and simulations which are based on S-Curves.

24
Q

What is other special curve?

A

Many companies have their own formulas for cash-flow forecasting.

25
Q

How would you reflect retention release in Cash Flow Forecast?

A

Subject to contract rectification period.
• ½ retention released at Practical Completion Date.
• ½ retention released at valuation after issue of Certificate of Making Good Defects.

26
Q

How would you put together a Cash-Flow Forecast?

A

Pre-Construction:
• Collect PM Programme and Cost Plan.
• On graph reflect X-Axis construction duration and Y-Axis total project cost.
• Determine each packages value and time taken.
• Reflect the anticipated monthly expenditure for overall project during construction period.
Post-Construction:
• Update S-Curve using Contract Sum and Contractor’s proposed programme
• Until Contractor provides their own Cash Flow Forecast – ask to update this regularly.

27
Q

What are the disadvantages of Cash-Flow Forecasting?

A
  • Projection only – level of accuracy limited.

* Unforeseen factors – COVID-19, strikes – therefore cash flow must be updated regularly

28
Q

What is front-loading?

A

Forecasts costs at start of project higher than they will be, providing higher payments earlier i.e. Demolition.

29
Q

What is contingency?

A

Risk Allowance for any foreseen or unknown risks on a project.

30
Q

How is contingency calculated?

A

Quantification of Risk.

31
Q

How would you calculate contingency allowance?

A

At BPT we typically use Percentage Addition - %.

This is because we have multiple projects across different sectors to benchmark across, rare where the contingency % is exceeded.

32
Q

How frequently should contingency be reviewed?

A

Every time budget and forecast updated.

33
Q

What are the different categories of contingency?

A
  • Allocated contingency – likely costs allocated to specific items.
  • Unallocated contingency- likely costs not specified – unlikely/can’t be accurately predicted.
34
Q

How do you manage contingency?

A
  • Typically held and released at the end of a project

* Or can be deducted to account for any changes/variations during the works.

35
Q

What is final account?

A

Conclusion of Contract Sum – determination of final monies employer will pay contractor, including any changes throughout the duration of the works.

36
Q

Where can a QS get guidance on Final Accounts?

A

RICS Guidance Note – Final Account Procedures

37
Q

What would be included in a Final Account?

A
  • Contract Works
  • Provisional Sums
  • Fixed Costs = Contract Sum
  • Day works
  • Contract Instructions
  • Anticipated Variations
  • Loss and Expense
38
Q

How should a Final Account be structured?

A

No firm rules about structure of final account.

39
Q

What is the Final Account procedure under JCT?

A

Depends on Contract Selection.

40
Q

What is the process for agreeing Final Account under JCT Standard Building Contract?

A

Within 6 months of Practical Completion – Contractor submits documents necessary for adjusting Contract Sum to Architect/CA or Quantity Surveyor (if so instructed).

Within 3 months after receipt Architect/CA or Quantity Surveyor (if so instructed);

  • Ascertain loss and/or expense notified by Contractor and or not previous ascertained.
  • Quantity Surveyor shall prepare statement showing all adjustments.
  • Architect/CA shall issue contractor copies of Final Statement.
41
Q

What happens if Contractor fails to issue supporting information?

A

After expiry of 6 months, Architect/CA may give contractor one-month notice – otherwise Final Statement can be determined based on their own documentation.

42
Q

What is included in a Final Certificate?

A
  • The Contract Sum, as so adjusted and;
  • Sum of amounts already stated in Interim Certificates plus advance payments and any sums paid after issue of the latest interim payment certificate
43
Q

When is a Final Certificate issued under Standard Building Contract?

A

2-months from whichever of the following occurs last:

  • End of Rectification Period.
  • Certificate of Completion of Making Good.
  • Date of Final Adjustment issue.

Due date Final Certificate or within 2 months of whichever occurs last.

44
Q

What is the process for agreeing Final Statement under JCT Intermediate Contract?

A
  • Same as SBC
  • 6 months – contractor submit documentation
  • 3 months – Final Valuation (Adjusted Contract Sum)
45
Q

When is a Final Certificate issued under Intermediate Building Contract?

A

Within 28 days of whichever occurs last – Final Certificate to be issued:

  • End of Rectification Period.
  • Certificate of Completion of Making Good.
  • Date of Statement / Adjusted Contract Sum issued to contractor.

Due date Final Certificate or within 28 days of whichever occurs last.

46
Q

What is the process for agreeing Final Statement under JCT Minor Works Contract?

A

Within 3 months of Practical Completion (if not stated otherwise) – Contractor submits documents

Architect/CA to determine final payment within 28 days of receipt.

Due date for Final Payment with be 14 days from due date of final payment.

47
Q

What is the process for agreeing Final Statement under JCT Design & Build Contract?

A

Within 3 months of Practical Completion – Final Statement to be submitted by Contractor.

Employer to agree final account [No reference to time period]

Contractor must also provide supporting documents as reasonably required.

48
Q

What if contractor does not submit within 3 months?

A

Employer can issue notice to contractor – if not submitted within 2 months, following expiary the employer can issue their own final statement.

49
Q

What is included under a Final Statement?

A
  • The Contract Sum, as so adjusted and;
  • Sum of amounts already paid by the Employer to the Contractor
  • Final payment – difference between two sums (balance due to contractor or from contractor).
50
Q

What is the final payment date under Design and Build?

A

1-month from whichever event occurs last:
• End of Rectification Period.
• Notice of Making Good Defects.
• Final Statement.

51
Q

What if Final Account cannot be agreed?

A

Employer or Contractor can issue notice of dispute prior to due date of final payment.

JCT contract provides provisions to refer to adjudication, arbitration or legal proceedings.

52
Q

How are Final Accounts determined under NEC Contracts?

A

No reference to final accounts as assumed final account is adjusted as project proceeds on basis of compensation event procedure followed.

NEC Requirement to report Early Warning Notice for Risk.

Effectively rolling final account therefore, last valuation date of last valuation and payment timescale.